10 More PMP Waterfall Questions to Brighten Your Day (71 to 80)

  Рет қаралды 9,895

David McLachlan

David McLachlan

Күн бұрын

⭐️⭐️⭐️ Get 35 Contact Hours / PDUs and 500 PMP Practice Questions in my Udemy course: www.udemy.com/course/ultimate...
✅✅✅ Or Get 52 ready-made Project Templates here: www.etsy.com/au/listing/11998...
To kick-start your career 🙂
I think these PMP Waterfall Questions are getting harder.
Questions 71 to 80. Enjoy - you can do it!
Timestamps:
00:00 Intro
00:31 Question 71: Raising a claim
03:10 Question 72: Rejecting a project charter
06:17 Question 73: Procurement planning
09:52 Question 74: Offsite resources
12:38 Question 75: Resource changes
15:50 Question 76: Problem solving
18:21 Question 77: Finding who can help
20:32 Question 78: Ideas for a new project
22:58 Question 79: Different project phases
25:39 Question 80: Managing with no experience
28:07 Never forget, you are amazing.
#PMP #projectmanagement #pmbok

Пікірлер: 24
@nafidpk1
@nafidpk1 Жыл бұрын
David, i think this is a very good way of teaching. It’s not just we are covering 10 questions, but you explain the steps deeply. Hence two benefits at a time: 1. Quality questions 2. Overall revision
@davidmclachlanproject
@davidmclachlanproject Жыл бұрын
Yes I agree! Funny you mention it, as there have been studies that show practice exams (and having to recall something) gives the highest chance of truly embedded learning.
@and5336
@and5336 Жыл бұрын
Can't believe I got Q73 correct. Using the mindset of 'what will you do next'. Approaching the senior management seemed correct to me. Option B would come after D.
@nafidpk1
@nafidpk1 Жыл бұрын
Bcz sometimes we have a mindset that try to resolve your things without going to senior management this is a common mindset, but here if we think our own organizational structure for anything higher value the chairman is required to approve even if the procurement is not a single source so that mindset is important and moreover it’s all about understanding the question well… My major issues is focusing quality time on question but once with David yes now focusing on question deeply and going thru all the options
@MrNikhilgherwar
@MrNikhilgherwar Жыл бұрын
Daily I see your video and that keeps increasing my confidence, thankd David!
@KarolinaBzukaa
@KarolinaBzukaa Жыл бұрын
hi I just passed few days ago, these videos help me a lot! thank you David!
@davidmclachlanproject
@davidmclachlanproject Жыл бұрын
Congratulations on passing your exam 🎉🙂
@semnaresh8339
@semnaresh8339 Жыл бұрын
Thanks @David your your effort❤️
@pdvpandi
@pdvpandi Жыл бұрын
question 73 I guessed the correct answer D
@shreyasichakraborty3292
@shreyasichakraborty3292 11 ай бұрын
8/10, incorrect: 73and 78, keeping a tab of my learning and score 🤩
@sameerdakhane1197
@sameerdakhane1197 7 ай бұрын
Hello Sir I am regular viewer of your channel. This is the best available. May I know which software you use to create these videos? BTW, what is above Target score? Thank you 😊
@s864008
@s864008 Жыл бұрын
Qu 76: When a problem is registered in an issue log, the owner of the issue should have been identified. The project manager has possibly checked the lessons learnt register before registering the problem as an issue. He/She did not find the solution and raised it as an issue.
@anandts6973
@anandts6973 Жыл бұрын
if conduct procurements is in action and seller has been selected then next work will have to be to frame a contract , without framing a contract what will the Sr mgmt approve? Awarding the contract will always come after contract has been framed.
@pdvpandi
@pdvpandi Жыл бұрын
drafting contact is not Project manager primary job it is procurement manager job he could be the senior manager.
@nafidpk1
@nafidpk1 Жыл бұрын
To add when the contract is high level PM can’t go and take decisions even if the procurement is not single source..
@felixc2867
@felixc2867 Жыл бұрын
I think the key is the final words saying 'proceed with the implementation'. Cant proceed unless you have approval so D is the answer. If 'proceed with the implementation' werent there B is accurate for the PM to have a contract drafted (not them actually doing it).
@enochjf
@enochjf Жыл бұрын
Is study hall really required for clearing PMP
@rickfox4068
@rickfox4068 Жыл бұрын
Ummm- Kind of confused on 74. If we already have a mandate on workers being onsite, why do we need to do an alternative analysis of off site workers?
@davidmclachlanproject
@davidmclachlanproject Жыл бұрын
I think the next question (75) is a good reason why 🙂
@nafidpk1
@nafidpk1 Жыл бұрын
Any analyze review action is the mindset
@djpershan
@djpershan 3 ай бұрын
@@davidmclachlanproject I did review question 75 however, regarding question 74, the question already states that PMO mandates works being onsite and the Resource Management Plan is about "HOW" we will manage resources. Isn't PMO mandating us using onsite works basically defining "HOW" we will use the resources and the reason why we need to update the Resource Management Plan? Plan Resource Management comes before Estimate Activity Resources on the order of processes.
@MisterStubstep
@MisterStubstep Жыл бұрын
Dang I missed 73 haha
@steffenfrank6804
@steffenfrank6804 Жыл бұрын
I think question 73 does not have a correct answer. The question states that the project is complex and high-value, but it does not say anything about the complexity, risk or value of the procurement. Not every procurement in a complex, high-value project is complex or has a high value. The RFQ could just be about cheap socket covers to be delivered at a fixed price, the cheapest bidder wins, which would probably not require senior management approval.
@nafidpk1
@nafidpk1 Жыл бұрын
High value is clear enough at times that it’s beyond PM s control. Honestly I’m discussing the Middle East concept, here when the slab of contract value passed certain million the higher management involvement comes before drafting the contracts
That's how money comes into our family
00:14
Mamasoboliha
Рет қаралды 12 МЛН
HOW DID HE WIN? 😱
00:33
Topper Guild
Рет қаралды 49 МЛН
How Many Balloons Does It Take To Fly?
00:18
MrBeast
Рет қаралды 156 МЛН
When You Get Ran Over By A Car...
00:15
Jojo Sim
Рет қаралды 34 МЛН
The Classic & Reverse Fishbone Diagram | A Whiteboard Training Video
14:25
i-nexus strategy software
Рет қаралды 40 М.
Eight Job Types in Project Management with Salaries and Job Openings
9:41
AGILE versus WATERFALL Project Plans
27:55
David McLachlan
Рет қаралды 18 М.
10 Really Hard Waterfall PMP Questions and Answers (51 to 60)
26:43
David McLachlan
Рет қаралды 14 М.
It's Time! 10 More PMP Waterfall Questions and Answers (21 to 30)
26:12
The ONLY thing you need to pass the PMP?
9:41
David McLachlan
Рет қаралды 32 М.
How to LEARN and Study FAST (4 Techniques)
7:59
David McLachlan
Рет қаралды 28 М.
That's how money comes into our family
00:14
Mamasoboliha
Рет қаралды 12 МЛН