kali ini kami akan membuat rumah minimalis sederhana dengan dana 50 juta, apakah mungkin?..
nah berikut data dibawah ini adalah total RAB nya.
URAIAN PEKERJAAN
PEKERJAAN PERSIAPAN
1.Uitzet & Bowplank
33.50m1 19,500 653,250 Rp 653,250 II
PEKERJAAN TANAH DAN PONDASI
1Galian tanah Pondasi
15.3336.500.700.60m3 50,000 766,500 2
Urugan sirtu bawah lantai t=30cm
10.9536.501.000.30m3 110,000 1,204,500 3
Pondasi Batu kumbung 30x60x60
1.1036.500.060.50m3 300,000 328,500 Rp 2,299,500 III
PEKERJAAN STRUKTUR
1Lantai kerja0.5536.500.300.05m3 750,000 410,625 2Kolom0.77110.023.50m3 3,750,000 2,887,500 3Balok0.1536.500.020.20m3 3,800,000 554,800 Rp 3,852,925 IV
PEKERJAAN DINDING
1Batu Bata Merah 1,344bh .Rp. 806,400
2Kalsiboard 1.2 x 2.4 (13bh )Rp 780,000
3.Finishing 1bh 800,000 800,000 Rp 2,386,400 V
PEKERJAAN ATAP/KAP
1
Baja Ringan dobel TASO C 75 x 0.75mm
100m2 15,000 1,500,000 2Asbes 180 x 8026bh 50,000 1,300,000 3
Batu bata gawel
1,005bh 600 603,000 Rp 3,403,000 Rp 5,789,400 VII
PEKERJAAN PINTU DAN JENDELA
pintu 804titik 1,000,000 4,000,000
Pintu kamar mandi
1titik 200,000 200,000 Rp 4,200,000 2Jendela
jendela 120 x 150
2titik 700,000 1,400,000
jendela 60 x 150
1titik 350,000 350,000 Rp 1,750,000 Rp 5,950,000 VIII
PEKERJAAN FINISHING DINDING DAN LANTAI
2
Lantai km/wc 25X25
1.50m2 145,000 217,500 Rp 217,500 IX
PEKERJAAN INSTALASI LISTRIK
1
Pekerjaan elektrikal
Instalasi lampu
6ttk 150,000 900,000
Instalasi stop kontak + MATERIAL
6ttk 160,000 960,000
Instalasi saklar + MTRL
5ttk 160,000 800,000 Instalasi MCB1ttk 150,000 150,000 Pipa Listrik5ttk 8,000 40,000
Kabel 50 meter engkel 2.5mm
1ttk 120,000 120,000 Rp 2,810,000 X
PEKERJAAN SANITARY
1KM/WCWC JONGKOK 1bh 600,000 600,000
Kran bak mandi
3bh 80,000 240,000 2Dapur
Kitchen sink - Stainless steel royal
1bh 550,000 550,000 Kran AIR1bh 150,000 150,000 Sanyo1bh 780,000 780,000 Septi tank1bis 1,650,000 1,650,000 Rp 3,970,000 XIIPEKERJAAN 1Pasir4rit 900,000 3,600,000 2Semen41sak 55,000 2,255,000 3
Besi Uk Ø 10 SNI Full
42bh 55,000 2,310,000 4
Besi Uk Ø 6 SNI Full
32bh 31,000 992,000 5
Baja Ringan TASO C 75 x 0.75mm
159m2 15,000 2,385,000 Rp 11,542,000 XIII
PEKERJAAN DAPUR
1Besi53.000.601.50bh 31,000 155,000 2Semen23.000.601.50sak 55,000 110,000 ongkos tukang 12.000.000 Rp 265,000 Rp 18,804,500 Grand Total 49.545.675Pembulatan Rp 50,000,000