Рет қаралды 6,925
Engine 22 dispatched for a fire alarm activation to the building next door. Follow up phone calls has Dispatch asking for an update if on scene crews see fire. Upon further investigation, yes fire was found on the 2nd floor and the Balance was sent. An aggressive search was done due to possible persons trapped in the bldg, residents were not home. Rescue1 reported a member low on air and to have a ladder put on the #2 side of bldg for egress. B-43 requested and extra 2&1 to scene for manpower. Heavy fire extends into the attic as engine 28 makes a push with 2 lines. Truck 15 crews working on ventilation on the roof encounter heavy fire coming from vent home and are forced off the roof. Extensive overhaul required on 2nd floor and attic.
3 -1¾" Lines in use
ON Scene:
Engines: 22, 31, 28, 33, 3
Trucks: 14, 15, 10, 5 FAST, Rescue1
Chiefs: B-43, B-46 & B-56
Support Staff: F-20, 40, 9, 11
Damages: $ 190K
9-22-2021 - Time Out: 23:53 hrs