Process of the project:
1. Pull the transformer with hydraulic power from the original place to the ready to lift place.
2. Lift the transformer with hydraulic jacks - remove the wheels - put steel and wood support and get ready to slide the transformer.
3. Load the transformer to the trailer with the hydraulic sliding system and secure the load.
4. Begin the transport.
5. Sliding the load from trailer to supports.
6. Lift transformer and put back the wheels.
7. Pull the transformer to the final place.
Machines that carry the transport to finish:
MAN TGX 680 8x4 with wsk
MAN TGA 660 8x4 with wsk
Goldhofer THP/SL 10 axles
Goldhofer 300mm lowbed for 300t capacity
4 Hydraulic lifting jacks 100 t capacity each
2 Hydraulic push jacks for slide the transformer
2 Hydraulic long pull jacks to place the transformer to the final place
The company Stavridis Special Transport & Cranes was founded in 1995. We are active in lifting and special transport of static blocks, steel constructions, wind turbines, transformers, steam turbines, generators, gas turbines, hydroelectric dams equipment, industrial and earthmoving equipment. In addition, we escort heavy vehicles, issuance of transit permits and road survey in Greece. Also the company undertakes logistic tasks of oversized pieces as it has 600 square meters covered and 20,000 square meters open land with a gantry crane.
Email: info@stavridis-crane.gr
Website: www.stavridis-crane.gr/
Facebook: / stavridis.sp. .
Instagram: / stavridis_s. .
Production: / teo_axio
#hydrauliclift #alsthom #hydraulicslippermakingmachine
#mantruck #heavytransport #heavyequipment #goldhofer #specialtransport #heavymachines #mantrucks #specialtransporter #heavymachinery #goldhoferthpsl #lowbed #transformer #hydraulic