Honnacotts M Week 40 - Slating continues, plaster-boarding, first fix electrics, truss ready plot 2

  Рет қаралды 80

Wrenwood Renovations

Wrenwood Renovations

Ай бұрын

Wk 40
• Plot 1 - work is virtually finished on the truss roof with dormers built and and structural boarding in place.
• Plot 2 - with scaffolding up, steel lintels are in ready for trusses to be fitted..
• Plot 3 - first rows of blocking starts.
• Plot 4 - dormers are readied for render. First fix electrics goes in.
• Plot 5 - Slating continues, the front being finished looking lovely. Slating starts on the back. Plaster-boarding progresses..
A 18-month project to create 5 beautiful, homes, inspired by old country buildings, filled with character combining old and new. A wealth of natural materials in energy efficient homes. Weekly updates on progress on our channel.
Music: Weekend by LesFM | lesfm.net/acoustic-background...
Music promoted by www.chosic.com/free-music/all/
Creative Commons CC BY 3.0
creativecommons.org/licenses/...

Пікірлер
Идеально повторил? Хотите вторую часть?
00:13
⚡️КАН АНДРЕЙ⚡️
Рет қаралды 10 МЛН
What it feels like cleaning up after a toddler.
00:40
Daniel LaBelle
Рет қаралды 92 МЛН
Задержи дыхание дольше всех!
00:42
Аришнев
Рет қаралды 3,8 МЛН
Why Haven't We Warmed to Porotherm in the UK?
8:34
Skill Builder
Рет қаралды 381 М.
Foxtail Meadow - Turfing, prepping paths and patio bases, rendering.
2:27
How to build a LOW MAINTENANCE timber decking base
27:41
Gosforth Handyman
Рет қаралды 124 М.
Low Cost Solution // LAYING PAVING SLABS
13:20
Rag 'n' Bone Brown
Рет қаралды 718 М.
Идеально повторил? Хотите вторую часть?
00:13
⚡️КАН АНДРЕЙ⚡️
Рет қаралды 10 МЛН