🔴 How to Apply Actual and Update Progress Works in Primavera P6

  Рет қаралды 9,536

Ahmad Setayandeh

Ahmad Setayandeh

Күн бұрын

Пікірлер: 14
@mohamedrami1009
@mohamedrami1009 5 ай бұрын
Hi I have a question, When i use Progress update and i select the Data-date i want, some of the tasks change the finish dates (only tasks with ongoing progress). Can you explain to me what to do to prevent this? thank you.
@GlobalProjectControl
@GlobalProjectControl 5 ай бұрын
Your question is not clear enough! Please note that after the progress update if you get delayed then the project forecast finish date will be shifted to the right!
@khankhankkkkkkkkkkkk
@khankhankkkkkkkkkkkk 3 жыл бұрын
All your lectures are very informative
@GlobalProjectControl
@GlobalProjectControl 3 жыл бұрын
Glad to hear that
@user-lm5eq6vu9y
@user-lm5eq6vu9y Жыл бұрын
thank you for introducing different parts of software, But in real project when do we use apply actuals and for what purpose?
@GlobalProjectControl
@GlobalProjectControl Жыл бұрын
If you need to update the Actual Progress as same as the Plan then you can use this part of the software.
@kambizradman7378
@kambizradman7378 11 ай бұрын
​@GlobalProjectControl thanks for that Ahmad. Once you have a percentage for duration % ( as an actual) and click on actual update what should be seen?
@ashumudgal
@ashumudgal Жыл бұрын
Really good !
@GlobalProjectControl
@GlobalProjectControl Жыл бұрын
I appreciate your feedback 🙏
@margaindra3516
@margaindra3516 3 жыл бұрын
I already checklist the autocompute box.. and apply actual ( with the same command of course), with the new data date from finish date planned but its not shifted and the checklist wont compute as Actual works, can you figure it out why this happened??
@GlobalProjectControl
@GlobalProjectControl 2 жыл бұрын
if you proceed the command base on the video, it should be work. but in case of any problem exist please join to GPC Group by below link for further clarification. 🌍 GPC Group : t.me/GlobalProjectControl
@standsforpeace9312
@standsforpeace9312 2 жыл бұрын
In the video, when you use update progress with selected activity, it is showing not started activities before data date, which is logically wrong. In order to move the not started activity after data date, you should schedule with the new data date (In this case Nov 10,21).
@GlobalProjectControl
@GlobalProjectControl 2 жыл бұрын
Yes, it is. But I want to present Apply Actual and Update Progress capability. In the real condition after each update, we should schedule the project in order to re-schedule the remaining work
🔴 How Resource Rate and its Overtime Factor Works in Primavera P6
7:39
Мы сделали гигантские сухарики!  #большаяеда
00:44
Fortunately, Ultraman protects me  #shorts #ultraman #ultramantiga #liveaction
00:10
Look at two different videos 😁 @karina-kola
00:11
Andrey Grechka
Рет қаралды 15 МЛН
🔴 Baseline Modification (Update Baseline)
9:01
Ahmad Setayandeh
Рет қаралды 4,9 М.
🔴 How to Create Recovery Schedule S-Curve
17:27
Ahmad Setayandeh
Рет қаралды 6 М.
import progress updates with actual dates to primavera p6
10:32
Planning Engineer FZE.
Рет қаралды 24 М.
How to Update a Schedule in Primavera P6
9:45
PJM Scheduling Services
Рет қаралды 25 М.
Recalculate Actual Units & Costs in P6, When Duration % Complete Changes
6:50
Мы сделали гигантские сухарики!  #большаяеда
00:44