How To Bulk Upload Resources Data to Primavera P6 Using Excel

  Рет қаралды 31,301

dptutorials

dptutorials

Күн бұрын

I got a request from our subscriber Shantanu to show How To Bulk Upload Resources Data to Primavera P6 Using Excel
So, let us see this in this tutorial in detail.
Most of us maintain all the scheduling data in excel as part of planning.
So, you have to keep it ready in the planning stage itself with all the required resources data including their naming nomenclatures.
For example, like this on resources part for a sample schedule. I have activity Id, name and Resource id and respective budgeted units maintained in Excel like shown in this video.
Watch this video for complete tutorial.
For Personalized detail learning, write to dptutorials15@gmail.com
If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.
***********************************************
★ My Online Tutorials ► www.dptutorial...
LEARNING RESOURCES I Recommend: www.dptutorial...
Subscribe for more Awesome Tutorials: goo.gl/NyAtg2
Support the Channel via shopping: ift.tt/2jH38PR
Tools for youtube vlogging:
• Laptop: amzn.to/2CaLFxJ fkrt.it/AM9ab_uuuN
• Canon 200D Camera: amzn.to/3d7jDR4 fkrt.it/AMz75_uuuN
• Benro Tripod: amzn.to/3exQoax fkrt.it/An1lm_uuuN
• Microphone: amzn.to/3c5lEvS fkrt.it/A2RHz_uuuN
• Collar Microphone: amzn.to/2X8DWrS fkrt.it/yL8kdQNNNN
• Screen recorder: techsmith.pxf....
• Boom Arm Stand: amzn.to/3extb87 fkrt.it/ypUD8QNNNN
• Zoom H1 Audio Recorder: amzn.to/2TNdHFj fkrt.it/ypb7WQNNNN
• Harison Softbox Studio Lights: amzn.to/3caGbzg fkrt.it/ypCaRQNNNN
• Chroma Key Green Screen: amzn.to/2M60mn4 fkrt.it/A3gnb_uuuN
• Background Support Stand: amzn.to/3dbACSv fkrt.it/A3cCb_uuuN
• Acoustic Foam Background: amzn.to/3gzFtyC fkrt.it/ypsGdQNNNN
• USB RGB LED Strip: amzn.to/36BpCLF fkrt.it/A3T_5_uuuN
• Wireless Mouse: amzn.to/2TPIrW7 fkrt.it/A3Bqz_uuuN
Note: This description contains affiliate links, which means at no additional cost to you, we will receive a small commission if you make a purchase using the links. This helps support the channel and allows us to continue to make videos like this. Thank you for your support!
***********************************************
You Can Connect with Me at:
KZfaq: / dptutorials
G+: ift.tt/2kAOpa6
Twitter: / dptutorials15
Facebook: ift.tt/2kfRnDi
BlogSpot: ift.tt/2kB14dh
Follow:
www.dptutorials.com
www.askplanner.blogspot.com
#dptutorials #Primavera #PrimaveraFree #resources #excelimport
Tags: -
P6:
primavera p6 training online, primavera p6, primavera p6 training, primavera p6 tutorial, oracle primavera, primavera p6 download, primavera 6, oracle primavera p6, primavera p6 free download, primavera project management, primavera project planner, primavera download, primavera online, primavera training, primavera software free download, youtube primavera, primavera tutorial, is primavera online easy, p6 online, primavera p6 complete video tutorial free download, critical path, oracle primavera, primavera p6, primavera, primavera software, construction project management software, project management software, project management books, microsoft project, project management courses, project management certification, online project management, project management tools, free project management software, project management training, best project management software, pmp certification, free project management tools, project management apps, microsoft project management, project management professional certification, google project management, ms project, agile project management, basecamp project management, project portfolio management, project management, project management system, scrum project management, open source project management, project management template, construction project management, project plan, project management professional,

Пікірлер: 55
@fadielrefai8372
@fadielrefai8372 13 күн бұрын
right to the points, thanks
@scottymac734
@scottymac734 7 ай бұрын
Very good. Right to the point. Best way to share tutorial info.
@yankov2206
@yankov2206 3 жыл бұрын
Bless you! Thanks. I have through about it and find your video. You better then me in this by 1 step! Best regards!
@dptutorials
@dptutorials 3 жыл бұрын
Thank you. You're welcome!
@zaidalfityan6856
@zaidalfityan6856 2 жыл бұрын
Thank you you saved my ass right before deadline You da best
@dptutorials
@dptutorials 2 жыл бұрын
Thanks a lot Zaid
@tylerguzinski6772
@tylerguzinski6772 3 ай бұрын
Very helpful! thanks!
@ramliramramli4330
@ramliramramli4330 3 жыл бұрын
Good example... giving me to explore others technique...as well
@dptutorials
@dptutorials 3 жыл бұрын
Glad it was helpful!, Sure will post more, please subscribe to channel and support.
@Aryanss5743
@Aryanss5743 3 жыл бұрын
Hi Sir.Your videos are too much helpful and informative. I have one request please can you make a video on how to calculate manpower for a project of atleast 5000 activities
@dptutorials
@dptutorials 3 жыл бұрын
Okay sure
@teesrajahaan7450
@teesrajahaan7450 3 жыл бұрын
Very nice, well done
@dptutorials
@dptutorials 3 жыл бұрын
Thank you! Cheers!
@bilelchaabane9862
@bilelchaabane9862 2 жыл бұрын
thanks a lot
@dptutorials
@dptutorials 2 жыл бұрын
You are most welcome
@kambizradman7378
@kambizradman7378 Жыл бұрын
in this point was useful. many thanks. Could you please generate a video on how to calculate manpower for a project over 4000 activities
@dptutorials
@dptutorials Жыл бұрын
Great suggestion!
@ramliramramli4330
@ramliramramli4330 3 жыл бұрын
Good guidance 🤠
@dptutorials
@dptutorials 3 жыл бұрын
Most welcome
@jithinv16
@jithinv16 2 жыл бұрын
hai superbbb
@dptutorials
@dptutorials 2 жыл бұрын
Thanks a lot..
@imdadhsheik138
@imdadhsheik138 2 жыл бұрын
Hai sir, In this video u have shown the excel which you already calculated the budgeted unit's could u please share more information how you have calculated the budgeted unit's.....
@dptutorials
@dptutorials 2 жыл бұрын
Yes, sure
@akhild69
@akhild69 Жыл бұрын
Hi, If multiple resources are to be assigned for each activity
@ravindrankrishnan2964
@ravindrankrishnan2964 2 жыл бұрын
Hi, Pls put Video for Resource uploading for all three type resources ( Labour, non labour and materials ) and for cost loading...
@feroskhan9529
@feroskhan9529 4 жыл бұрын
Yes, here created resources are assigned to the activities in XER since Resource ID column in excel sheet is filled with created ID's (T1, T2 & T3) respectively...
@dptutorials
@dptutorials 4 жыл бұрын
yes
@RamA-xd6bt
@RamA-xd6bt Жыл бұрын
Thanks for the details and is it possible to upload multiple projects at the same time also could you please elobarate on XER file while you import the data. Looking forward.
@dptutorials
@dptutorials Жыл бұрын
Not possible
@ramamohanannamaneni4010
@ramamohanannamaneni4010 Жыл бұрын
@@dptutorials Thank you
@sougatamitra9984
@sougatamitra9984 Жыл бұрын
Hi sir, I am working on a base plan of highway project with around 500 activities. I need to load multiple resources types with multiple budgeted quantities against each activity. Say earthwork in embankment will attract excavator, dumper, grader, vibrio roller, water tanker, borrowed earth etc. each having different budgeted resources quantities and different BOQ quantities as well. How to do this by excel export and import? Your kind support will help me a lot.
@dptutorials
@dptutorials Жыл бұрын
Yes, sure
@erkanakdogan7382
@erkanakdogan7382 2 жыл бұрын
I try this method too but idk in articles which i read dont recommend this method because it can cause some errors.thats why i always assign resources one by one in p6 not using excel
@juancarloshuaraccuizano9553
@juancarloshuaraccuizano9553 2 жыл бұрын
But try to do it and identify the possible wrong. I think it's an excellent video.
@rohithv3657
@rohithv3657 Жыл бұрын
How can we uniquely identify a container WBS element in primavera?
@scottymac734
@scottymac734 7 ай бұрын
Us the Filter tab when selecting fields in the export template.
@raghav051
@raghav051 2 жыл бұрын
Hi, Followed step by step. While importing the file, an error is occurring which is as below- The User Preferences used to create this Excel file are not the same as your current preferences. Importing this file could corrupt your data. Please refer to Help for more information about importing data from Excel. Are you sure that you want to continue? Can you pls help me out in this?
@dptutorials
@dptutorials 2 жыл бұрын
Hi, First export the schedule into excel to get the right format and then import post entering the data into the excel sheet.
@shakibulkabir5292
@shakibulkabir5292 2 жыл бұрын
How to add Rod,Cement, Stone under multiple activities???
@dptutorials
@dptutorials 2 жыл бұрын
create as separate resources
@feroskhan9529
@feroskhan9529 4 жыл бұрын
Is it possible to add more than 1 resources to an activity through Xel to Xer??How?
@dptutorials
@dptutorials 4 жыл бұрын
yes, it is. Its already shown in this video. you need to just enter the same in a new row for new resource.
@feroskhan9529
@feroskhan9529 4 жыл бұрын
I got it..For every new resource copy and paste the respective activities again and again...What if I put “comma” inbetween adding second resource in the same cell of the column( adding two resources inside same cell with comma in between)
@suryapadmaraju5573
@suryapadmaraju5573 2 жыл бұрын
I want to learn the offline course. Could you provide me.
@dptutorials
@dptutorials 2 жыл бұрын
sure, please write to info@dptutorials.com
@tedquinzon1305
@tedquinzon1305 3 жыл бұрын
is it possible to import new resources from excel to P6? if yes how.
@dptutorials
@dptutorials 3 жыл бұрын
Yes, It is like normal import only, File > Import > Select Spreadsheet-(XLS). I will try to publish a short video on this soon.
@tedquinzon1305
@tedquinzon1305 3 жыл бұрын
@@dptutorials Thank you, please do short video for this. I have already tried to import it but the NEW resources wont add to the resource list on P6.
@nevhil
@nevhil 2 жыл бұрын
@@dptutorials i think it is not possible to import new Resources to P6. Because Primavera can't read "Resource Type".
@rahulkulkarni8224
@rahulkulkarni8224 3 жыл бұрын
Can you please explain how to import the "Resource Names" because the exported excel file has an Asterix (*) in the Resource Name field and is therefore "Un-editable" and ignored by P6 during import.
@dptutorials
@dptutorials 3 жыл бұрын
You can replace the * in the excel
@amaninderkaur4145
@amaninderkaur4145 4 жыл бұрын
Hi dp... Please explain the process slowly! you are very fast sometimes...rest Kudos!
@dptutorials
@dptutorials 4 жыл бұрын
Sure aman, will consider this feedback.
Resource Loading in Primavera P6 - 5 Tips to make it EASIER
8:11
Plan Academy Inc.
Рет қаралды 28 М.
Kind Waiter's Gesture to Homeless Boy #shorts
00:32
I migliori trucchetti di Fabiosa
Рет қаралды 14 МЛН
Вы чего бл….🤣🤣🙏🏽🙏🏽🙏🏽
00:18
Blue Food VS Red Food Emoji Mukbang
00:33
MOOMOO STUDIO [무무 스튜디오]
Рет қаралды 5 МЛН
Import Cost from excel to primavera 6
7:40
Planning Engineer FZE.
Рет қаралды 62 М.
COST LOADING FROM BOQ IN PRIMAVERA P6 || PRIMAVERA P6 TUTORIALS
5:15
Manpower Resource Loading including S-curve in Primavera P6
13:30
🔴 How to Load Multiple Resources in P6 By Excel
15:52
Ahmad Setayandeh
Рет қаралды 8 М.
Primavera P6: How to make S Curves in Primavera P6
19:07
Zero Float
Рет қаралды 211 М.
How to Cost Load a Schedule in Primavera P6
9:57
PJM Scheduling Services
Рет қаралды 19 М.
Import Resources from Excel to P6
11:32
PJM Scheduling Services
Рет қаралды 8 М.
Kind Waiter's Gesture to Homeless Boy #shorts
00:32
I migliori trucchetti di Fabiosa
Рет қаралды 14 МЛН