Import Progress from Excel to Primavera P6

  Рет қаралды 9,619

PJM Scheduling Services

PJM Scheduling Services

Күн бұрын

To request a live help session with Pat, visit our website at www.pjmss.com/

Пікірлер: 15
@sarah-janefirth1951
@sarah-janefirth1951 Жыл бұрын
Hi Pat, these videos are really useful as I'm moving from using MS Project to P6 for a new job role so I really appreciate the work you put into these videos!
@MissTopDJ007
@MissTopDJ007 2 жыл бұрын
Thank you so much for creating these series on P6! I'm currently preparing myself to switch from Cost Control to Schedule Control.
@PJMScheduling
@PJMScheduling 2 жыл бұрын
Thanks for the kind words! I also started off in cost controls and switched to scheduling early in my career. The cost control background will serve you well!
@Naved1231
@Naved1231 3 ай бұрын
Were you able to make the switch? If yes, do you think its worth it? I want to move to cost control but not sure if it will be a wise decision.
@Mileyrubymiles
@Mileyrubymiles 9 ай бұрын
This video rescued me, thank you so much
@muhammadsaifullah8519
@muhammadsaifullah8519 2 жыл бұрын
Very informative tutorial.
@jessicaelizabethperezmelia50
@jessicaelizabethperezmelia50 Жыл бұрын
Hi pat, just a question if you have resources asigned how do you update the progress?
@ryane1383
@ryane1383 2 жыл бұрын
Do you have a troubleshooting guild for importing excel schedules? When I go through the import process nothing gets updated
@PJMScheduling
@PJMScheduling 2 жыл бұрын
I have quite a few tutorials on my channel for importing from excel to P6. Let me know specifically what you are trying to import from excel, and I may have a video for it and can point you in the right direction. If you're not able to find what you're looking for online, feel free to reach out to me on our website at pjmss.com if you want to set up a live tutoring session with me and we can walk through it.
@MrJithingopal143
@MrJithingopal143 8 ай бұрын
How we knows our data date while scheduling
@PJMScheduling
@PJMScheduling 8 ай бұрын
Click the "Tools" tab at the top of the screen, and click "Schedule". It will display the data date.
@MrJithingopal143
@MrJithingopal143 8 ай бұрын
@@PJMScheduling so we doesn’t need to change the date which coming as default.some times I noticed that while doing it entire schedule dates are changing
@PJMScheduling
@PJMScheduling 8 ай бұрын
@@MrJithingopal143 Try going to "Schedule Options" under schedule, and uncheck "Schedule automatically when a change affects dates". That should fix your issue. You can then manually reschedule the program after you make a change to recalculate the date.
@bhushankhadtale996
@bhushankhadtale996 Жыл бұрын
Hello Mr Pat, thank you for this useful video, as i am trying to import the excel sheet in P6, i am getting an error "An application event has been intercepted. Please note the event code for reference. Event code TPCAT-1067-C". Kindly suggest me how to fix this. Best Regards
@PJMScheduling
@PJMScheduling Жыл бұрын
So hard to know without looking at the excel file! But, a few things I would check for are: -Column headers are named correctly. -Required tabs are there and named correctly. -The actual data fields have the correct formatting. -There are no spaces in the rows. If you're still stuck - I do offer tutoring at pjmss.com for a fee. Feel free to reach out through the site and we can take a look together.
Import Descriptions from Excel to P6
7:16
PJM Scheduling Services
Рет қаралды 1,3 М.
Import Costs from Excel to Primavera P6
11:26
PJM Scheduling Services
Рет қаралды 2,5 М.
The Giant sleep in the town 👹🛏️🏡
00:24
Construction Site
Рет қаралды 20 МЛН
If Barbie came to life! 💝
00:37
Meow-some! Reacts
Рет қаралды 74 МЛН
Pool Bed Prank By My Grandpa 😂 #funny
00:47
SKITS
Рет қаралды 20 МЛН
import progress updates with actual dates to primavera p6
10:32
Planning Engineer FZE.
Рет қаралды 24 М.
Import Resources from Excel to P6
11:32
PJM Scheduling Services
Рет қаралды 8 М.
Full P6 Tutorial: Cost Loading with Expenses
19:37
PJM Scheduling Services
Рет қаралды 4,5 М.
36.  Export and Import in Primavera P6
15:16
Osama Saad
Рет қаралды 13 М.
How to Update a Cost Loaded Schedule in Primavera P6 - The Right Way
10:03
PJM Scheduling Services
Рет қаралды 5 М.
The Giant sleep in the town 👹🛏️🏡
00:24
Construction Site
Рет қаралды 20 МЛН