I confess I had to research this one... The distinction between resource leveling and resource smoothing is not one I was clear on. The message, however, is clear: resource optimization refers to both and is something to tackle, to make your project efficient.
@Onlinepmcourses6 ай бұрын
Thank you for watching. Please support the channel and all the free content I provide. - Like, comment, and subscribe to the channel. - Why not join my community, free! Sign-up at onlinepmcourses.com/assets440251/the-onlinepmcourses-newsletter/ - And to show maximum appreciation, use the $ Thanks button, under the video, to make a small donation with a highlighted comment.
@Jasmine-cn4wc6 ай бұрын
adaptability and pragmatism in project management is crucial since real-world scenarios often call for a blend of approaches tailored to specific projects. thanks for yet another great video!👍
@Onlinepmcourses6 ай бұрын
Thank you - I could not put it better myself!
@InfluentialPMO6 ай бұрын
Very helpful video, and well explained 👍
@Onlinepmcourses6 ай бұрын
Thank you very much, Stuart.
@viciwo33964 ай бұрын
Well explained!
@Onlinepmcourses4 ай бұрын
Thank you!
@afrahpalekar75914 ай бұрын
Very well explained
@Onlinepmcourses4 ай бұрын
Thank you!
@Krajnish1754 ай бұрын
👏
@Onlinepmcourses4 ай бұрын
Tx!
@amar6705Ай бұрын
this was not clear for me as compared to many of your other videos. Can you please mae anther Video on this topic
@OnlinepmcoursesАй бұрын
I'm not sure I know a better way to explain this, so what is it you did not understand? If you can pin down what is not clear, I can try to respond to clarify it for you.
@amar6705Ай бұрын
@@Onlinepmcourses . Thanks a lot for your response. this means a lot. in terms of the query, resource levelling was better understood but in terms of images for resource smoothing what is the yellow color that is above the resources. To be precise what happens to the extra resource that are added in the project ?
@OnlinepmcoursesАй бұрын
@@amar6705 In the resource smoothing diagram, the blue bars are the available resources applied to the plan. The hatched bars represent work reallocated to a time when resources can be available. The orange bars represent additional resources brought in to optimize capacity.