PMBOK® Guide: Project Schedule Management- Lead and Lag

  Рет қаралды 41,409

iZenBridge Consultancy Pvt Ltd.

iZenBridge Consultancy Pvt Ltd.

Күн бұрын

Sometimes we need to either speed up the dependent activities or delay the dependent activities while keeping in the relationship as is. This is the purpose of Lead and Lag.
Lead:
Lead means ahead of time, go a little bit fast. In the case of Finish-to-Start relationship, whatever time you want to lead, you need to reduce the start time of next activity by that time. For example, in the case of 2 days as lead time in FS relationship = ST (Start time)-2 Days.
Lag: The lag time is added in the actual start date of the next activity. For example, in the case of building and painting, you say that first let me finish the product and then after a gap, I want to start painting. You need a gap of certain days before you start painting, so this is lagging time. A duration where no work is done. So leading refers to work done in parallel by 2 activities whereas lagging means giving a gap of some duration between 2 activities.
In Simple language Lead is something running ahead as speed and lag is an amount of gap introduced in between two activities.
You can explore the videos for the complete course here
www.izenbridge...
The Project Management Professional (PMP), PMBOK, The Agile Certified Practitioner (PMI-ACP), and The Professional in Business Analysis (PMI-PBA) is a registered mark of the Project Management Institute, Inc.
PMBOK is a registered mark of the Project Management Institute, Inc.
Materials in this video are based on the text, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute Inc., 2017.
The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.
#pmptraining #pmpexam #pmpvideos

Пікірлер: 68
@daisyduck6171
@daisyduck6171 3 жыл бұрын
Best PMP videos. This instructor is the absolute best. I paid a lot of money for PMP prep classes. But nothing beats this. THANK YOU!!!!
@izenbridge
@izenbridge 3 жыл бұрын
Thank you for checking our PMP videos, we do have our Live Online Program on PMP, you can find details here : www.izenbridge.com/pmp/online-course/
@djhnbmdjhnb3581
@djhnbmdjhnb3581 5 жыл бұрын
Hi !, Yesterday I have cleared my PMP certification, your videos have helped me a lot. Thank you
@izenbridge
@izenbridge 5 жыл бұрын
Heartiest Congratulations!!! and Thank you Dharmik, for exploring our content . Good to know that our content was helpful to you. You can connect with us at sales@izenbridge.com for renewal of your PMP credentials.
@kshitijrathod3969
@kshitijrathod3969 Жыл бұрын
Hello Sir Can you guide me to clear the PMP exam? I mean, what questions do they as, and which chapter is to more focus of? Any best approach?? Thank you in advance
@findmaheshpatil
@findmaheshpatil 4 жыл бұрын
It’s takes immense courage to share the true and pure knowledge with the world. keep sharing and imparting knowledge to aspiring and growing Project/program managers. Appreciate all your efforts.
@izenbridge
@izenbridge 4 жыл бұрын
So nice of you!! Keep exploring iZenBridge KZfaq Channel. To know more about iZenBridge training programs, please visit -www.izenbridge.com/landing/youtube/Saket-Bansal/
@waqarulhassan2673
@waqarulhassan2673 4 жыл бұрын
finally, someone explained it well. Thank you!
@izenbridge
@izenbridge 4 жыл бұрын
Glad it was helpful! To know more about PMP program by Saket Bansal, please visit - www.izenbridge.com/pmp/online-course/
@MUHAMMAD-hu4sn
@MUHAMMAD-hu4sn Жыл бұрын
Great efforts done to promote knowledge best platform to learn Project management
@izenbridge
@izenbridge Жыл бұрын
Thanks a lot, In case you are exploring PMP certification, you may want to visit our PMP Program Page www.izenbridge.com/project-management/pmp-certification-training
@mehboobalam6522
@mehboobalam6522 3 жыл бұрын
Finaly i got what i searchedTHANK YOU SOO MUCH
@izenbridge
@izenbridge 3 жыл бұрын
Glad you liked it!! To know more about iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/ It is complete and comes with an end to end support.
@virginiasanchez3282
@virginiasanchez3282 2 жыл бұрын
Wonderful explanation... Very clear.. Thank you for the content...
@izenbridge
@izenbridge 2 жыл бұрын
Thank you, and if you wish to check some videos on PMP Mock Questions, here is the playlist kzfaq.info/sun/PLWcvFkRbuunnr8X3QM0pfeTUpi5o55gQl
@shailjaankur
@shailjaankur Жыл бұрын
Superb..
@ebeleero708
@ebeleero708 2 жыл бұрын
You are an awesome teacher.
@izenbridge
@izenbridge 2 жыл бұрын
Thank you.
@dineshkapoor5511
@dineshkapoor5511 4 жыл бұрын
Thanks for this video Sir, this has helped a lot and clear understanding between lead and Lags.
@izenbridge
@izenbridge 4 жыл бұрын
Glad to hear that!! To know more training programs, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
@rajneesh66
@rajneesh66 5 жыл бұрын
Clear and good explanation. Thanks for your informative Videos.
@izenbridge
@izenbridge 5 жыл бұрын
Thank you !! Raj, for exploring and liking our content In Continuation to it, you can explore our video on Funding Limit Reconciliation & S-Curve kzfaq.info/get/bejne/prZ0nriEkrvapqs.html
@shommytv
@shommytv 4 жыл бұрын
So extremely helpful. You helped me make a breakthrough.
@izenbridge
@izenbridge 4 жыл бұрын
Glad you enjoyed it! To know more about Saket training program , please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
@sshals09
@sshals09 4 жыл бұрын
You are amazing! Great Teacher
@izenbridge
@izenbridge 4 жыл бұрын
Thank you! 😃To know more, training programs, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
@rajpootone8636
@rajpootone8636 Жыл бұрын
Leads can only be applied to activitied with finish to start.Lags on the other hand can be applied to all relationdhips.
@zenu1982
@zenu1982 2 жыл бұрын
Thank you!
@izenbridge
@izenbridge 2 жыл бұрын
You're welcome!
@shasankv85
@shasankv85 3 жыл бұрын
Excellent Work
@izenbridge
@izenbridge 3 жыл бұрын
Thank you! Cheers! We do run PMP Program and here you can find details of same : www.izenbridge.com/pmp/online-course/
@andrewleong8643
@andrewleong8643 3 жыл бұрын
Excellent explanation
@izenbridge
@izenbridge 3 жыл бұрын
Glad you liked it!! keep exploring iZenBridge YoutTube Channel. To know more iZenBridge training programs, please visit - www.izenbridge.com/
@musaibshaikh5075
@musaibshaikh5075 4 жыл бұрын
Wonderfully explained
@izenbridge
@izenbridge 4 жыл бұрын
Thanks for your kind words!! Keep exploring iZenBridge KZfaq Channel.
@sathish137m
@sathish137m Жыл бұрын
Thank you so much Guru
@izenbridge
@izenbridge Жыл бұрын
You're most welcome
@anasahmed6305
@anasahmed6305 2 жыл бұрын
well explained!
@izenbridge
@izenbridge 2 жыл бұрын
Thank you
@swaminathan4223
@swaminathan4223 3 жыл бұрын
Thanks a lot
@masyasali2011
@masyasali2011 Жыл бұрын
It helped, thanks
@izenbridge
@izenbridge Жыл бұрын
Glad it helped
@platelet9999
@platelet9999 2 жыл бұрын
Your explanation is logical and clear. But figure 6-10 Examples of Lead and Lag in the PMBOK 6th edition is not clear and is confusing. Their examples seem to be switched for Lead and lag.
@izenbridge
@izenbridge 2 жыл бұрын
If you are preparing for PMP, you do not have to study PMBOK , you better focus on PMI's content for PMP. Consider joining our program on PMP here: www.izenbridge.com/pmp/online-course/
@husseinalm3025
@husseinalm3025 5 ай бұрын
I have a few questions, is LEAD/LAG established before construction begins as in during the scheduling stage OR developed during the construction stage as its ongoing? and if LEAD/LAG are established before construction begins, then does that mean the schedule is flawed? as in it could have been avoided by better scheduling and could the project manager freely decide to ignore the LAG time and keep working OR ignore the LEAD time and stick to actual activity time OR is he obligated to follow LEAD/LAG? so, does that means LEAD/LAG is superior to the actual start/finish time for each activity and the manager MUST follow it OR its optional and it just attempts to improve the schedule ?
@husseinalm3025
@husseinalm3025 5 ай бұрын
for example, we have (activity A "F to S" "-2days" activity B), does it mean that, activity B MUST start 2 days before activity A finishes 'OR' activity B COULD start 2 days before activity A finishes? Is it a MUST OR a COULD?
@izenbridge
@izenbridge 5 ай бұрын
in general situations you boil the egg and wait for 5 min to peel it, why you plan this Lag? Because it make sense , if you are in hurry you may take extra pain to save this 5 min and peel it early, this decision to increase the delay or reduce the delay you take based on situation at head. In Project management any thing we do we do in planning and keep revisiting it to improve our planning and execution, so you do plan lead and lag when needed and you do adjust in execution when needed. You as PM do it for the benefit of the project.
@sharifahintanamiraalqadri4065
@sharifahintanamiraalqadri4065 4 жыл бұрын
Thanks sir. Really clear
@izenbridge
@izenbridge 4 жыл бұрын
Glad it helped. To know more about complete PMP program, please visit - www.izenbridge.com/pmp/online-course/
@mazheribrahim7686
@mazheribrahim7686 4 жыл бұрын
Well explained
@izenbridge
@izenbridge 4 жыл бұрын
Thanks for your kind words!! To know more about complete PMP program, please visit -www.izenbridge.com/pmp/online-course/ It comes with an end to end support
@gurjotsingh6010
@gurjotsingh6010 3 жыл бұрын
ustaad
@antoniobiancofiore2396
@antoniobiancofiore2396 4 жыл бұрын
is this correct wrt Lead and Lag in using "painting" as the 2nd activity....for example classrooms 1,2,3, & 4 are to be drywalled, taped and prepped before paint but rather than start the painting activity on day 6 you want to start the painting on day 5 which means you begin painting classroom 1 & 2 while classrooms 3 & 4 are being completed?......this is assuming that each classroom is being drywalled, taped and prepped for paint one at a time this classroom 1 & 2 are done by day 5...is this a good example of lead?
@izenbridge
@izenbridge 4 жыл бұрын
Yes, you can say it.
@vishwajeetnaib2507
@vishwajeetnaib2507 2 жыл бұрын
Is lead applicable to all kinds of processes? I guess it is applicable only to FS
@izenbridge
@izenbridge 2 жыл бұрын
The lead and Lag is applied to all relation, technically its reducing the start date or delaying the start date, the relation will help in finding the start date.
@batoolhijjawi3114
@batoolhijjawi3114 4 жыл бұрын
Good 👍🏻
@izenbridge
@izenbridge 4 жыл бұрын
Glad it was helpful! To know more complete PMP program, please visit - www.izenbridge.com/pmp/online-course/
@anhtiennguyen
@anhtiennguyen 4 жыл бұрын
yeah lead means..leading, and lag means lagging. As clear as mud
@izenbridge
@izenbridge 4 жыл бұрын
Happy to know that you liked video, to know more about Saket training programs, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
@mustafasatc7660
@mustafasatc7660 3 жыл бұрын
I am a bit confusing. lag time is ok. But what is the difference between fast tracking and lead time. are they similar?
@izenbridge
@izenbridge 3 жыл бұрын
It is right to say than when we apply fast-tracking we apply Lead , we also sometime remove dependencies when we do fast tracking and run things in parallel
@mustafasatc7660
@mustafasatc7660 3 жыл бұрын
@@izenbridge thank you
@harshadshinde4388
@harshadshinde4388 2 жыл бұрын
Sir, does duration of dependent activity changes with addition of lead & lag ??
@izenbridge
@izenbridge 2 жыл бұрын
The start date will get impacted but not the duration (mean difference of end and start date).
@wana12345able
@wana12345able 4 жыл бұрын
excellent
@izenbridge
@izenbridge 4 жыл бұрын
Thanks for your kind words!! Keep exploring iZenBridge KZfaq Channel.
PMBOK® Guide : Plan Risk Responses Strategies for Threats
11:29
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 21 М.
PMBOK® Guide: Motivational Theory -Maslow's Hierarchy of Needs
10:21
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 8 М.
Bony Just Wants To Take A Shower #animation
00:10
GREEN MAX
Рет қаралды 7 МЛН
Little brothers couldn't stay calm when they noticed a bin lorry #shorts
00:32
Fabiosa Best Lifehacks
Рет қаралды 21 МЛН
PEDRO PEDRO INSIDEOUT
00:10
MOOMOO STUDIO [무무 스튜디오]
Рет қаралды 19 МЛН
PMBOK® Guide: Schedule Compression - Difference between Fast-Tracking and Crashing
8:18
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 23 М.
Leads and Lags with examples
11:21
PMC Lounge
Рет қаралды 9 М.
Precedence Diagramming Method (PDM) in project management
19:09
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 51 М.
Agile Release Planning - Project Management Professional - iZenBridge
9:07
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 74 М.
PMBOK® Guide: Plan Risk Responses Strategies for opportunities
8:38
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 9 М.
PMBOK® Guide Sixth edition: Difference between Total Float & Free Float
7:40
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 101 М.
PMBOK® Guide-Sixth edition : Earned Value Management Analysis
10:08
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 143 М.
Funding Limit Reconcilation & S-Curve
9:28
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 11 М.
Project Management Career - Is it Right For Me? (Let's be Real)
19:04
PM Perspective
Рет қаралды 544 М.
Bony Just Wants To Take A Shower #animation
00:10
GREEN MAX
Рет қаралды 7 МЛН