PMP Exam Questions 2023 (June) and Answers Practice Session | PMP Exam Prep |PMP for project manager

  Рет қаралды 10,307

PMPwithRay

PMPwithRay

Күн бұрын

Пікірлер: 80
@PMPwithRay
@PMPwithRay 8 ай бұрын
►►► If you are preparing for the PMP Certification in 2024, join my FREE Webinar for PMP Exam Prep: event.webinarjam.com/channel/pmpwithray2024
@sadecekul7774
@sadecekul7774 10 ай бұрын
Question 5: right answer should be C. They are in the review and there is a problem with aligning DoD. They can discuss the issue in the retro. Because retro will start right after review meeting. İn answer B, you don’t raise any issue in the retro meaning no discussion about the important matter. Also there is no design phase in agile. You can discuss all stories in the planning session.
@PMPwithRay
@PMPwithRay 10 ай бұрын
Hi, your line of thought is incorrect. Please re-watch the explanation which explains why B is correct. Discussing this in retro might help in future but it will not help to clear the mess out of the current situation.
@LyricalMurderer1
@LyricalMurderer1 5 ай бұрын
But the problem is that you are already done with the sprint review which is at the end of your iteration. Your increment doesn’t meet the DoD so you need to address that at the earliest. It doesn’t make sense to do it in the sprint review itself. Retro is a great place to discuss DoD because that’s still prior to the next sprint… no need for an unnecessary brainstorming session. Also, I realize this doesn’t explicitly say we are doing Scrum, but the use of the term “sprint” implies it. In Scrum the retro is the best place to discuss and modify the DoD.
@markxingguo1226
@markxingguo1226 4 ай бұрын
@@LyricalMurderer1 yes some exam questions providers find it hard to admin the mistake or ambiguity
@qhakazilemathebula3953
@qhakazilemathebula3953 3 күн бұрын
@@LyricalMurderer1 I fully agree with you here.
@cook4jinn69
@cook4jinn69 Жыл бұрын
Hi Ray, I want to thank you as I passed the PMP last Friday with 3 AT. Your course," PMP Exam-PMI New Format 2023 Mock Simulator (PMBOK7 Updated)" is one of the materials I used for the preparation. It is extremely helpful and it only took about 2 weeks. Thank you!
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for watching and commenting!
@metroswiftmovers1284
@metroswiftmovers1284 5 ай бұрын
Ray the answer to question 5 should be C . They are already past the design stage. Certainly B cannot be the answer right? any one else agrees?
@PMPwithRay
@PMPwithRay 5 ай бұрын
Hello, the correct answer and the explanation to the same is mentioned in the video.
@ranjitraja-t4l
@ranjitraja-t4l 26 күн бұрын
@@PMPwithRayHello Ray, Question asks us how should the manager tackle the situation and not asking how he could have avoided. Answer C, since the issue raised during sprint review (meaning at the end of the iteration), so this could have been parked during the sprint review and discussed in detail during the sprint retrospective. Answer B, if question is asked how could the PM have avoided. Please let know if my understanding on the same is correct. Thanks.
@alinaabdurazakova974
@alinaabdurazakova974 7 ай бұрын
Hello Ray, thank you so much for your videos and explanations on the way, very helpful! I stuck on the question 4 though. Considering servant leadership approach I thought choosing option D (engage human resource to create a plan to avoid layoffs) is more correct one than option C (perform a benefit management plan - why it does make more sense if management already sees a benefit?). Thank you if you answer the question!
@PMPwithRay
@PMPwithRay 7 ай бұрын
Hello, I believe I have explained the reasoning within the video itself. I would suggest you rewind & rewatch that section again. Timestamps are provided in the video description for your reference.
@turnover1618
@turnover1618 6 ай бұрын
Q5. As per tge Q text, tge project sprint already reached testing and acceptance criteria not met. Hence answer should be D. Definitely if the question was how the situation should have been tackled to avoid impacts, B is the answer. There is a language problem in the question unfortunately...
@PMPwithRay
@PMPwithRay 6 ай бұрын
Hello, in the PMP Exam, there will be Q's of such dubious nature. Skill is to test your understanding of how you can navigate through complex wordings within Q.
@turnover1618
@turnover1618 6 ай бұрын
@PMPwithRay yes, tricky Qs expected in exam. But that is not what I meant. Yet, for this particular sample test question, the answer B given is clearly not matching the question as I commented. It is understood this is not really a real 100% pmp question/ answer (at least the wording).
@simonoganga5956
@simonoganga5956 Жыл бұрын
Great Job Ray, you make it so easy to understand.
@PMPwithRay
@PMPwithRay Жыл бұрын
I appreciate that! Thank you Simon for watching and commenting!
@georgethomas7209
@georgethomas7209 10 ай бұрын
Hi Ray, firstly amazing questions and explanations, very helpful. question 5 is a bit tricky as the phrasing of “the product has not meet the acceptance criteria” suggests to me that development for this product is done and therefore design was also done. Therefore C seems like a viable option as it provides learning to address in a subsequent iteration. Can you please provide some clarification on the interpretation?
@PMPwithRay
@PMPwithRay 10 ай бұрын
Hi George, there is nothing wrong in your line of thought, except for the fact that the question stem is asking 'what should the PM do now to tackle the situation' rather than 'what should the PM do to avoid this in the subsequent iteration'...hence, tackling it in the design phase would make sense.
@sharadlgsi
@sharadlgsi Жыл бұрын
In question 5, its mentioned that DoD problem was highlighted in SPRINT REVIEW meeting. Generally there is not much gap between REVIEW and RETRO meetings so option C looks fair choice. If ans D is correct then how does DESIGN Phase comes earlier than RETRO? Any thoughts?
@PMPwithRay
@PMPwithRay Жыл бұрын
The retrospective happens at the end of a sprint and a review happens during a sprint. Within a sprint as well, the design comes before testing.
@sharadlgsi
@sharadlgsi Жыл бұрын
@@PMPwithRay first of all thanks for reply. Yes i understand that Retro happens at end of the sprint but Review is also during the end state of sprint (before retro) . My doubt was how the design phase comes between REVIEW and RETRO.
@PMPwithRay
@PMPwithRay Жыл бұрын
Hi, it might happen that the design modules get delivered is phases to the product development team, right? That way, outputs of one agile team become input for another agile team. Also, please note that a product iteration may take multiple sprints to deliver. So, retro does not happen till all the sprints are over.
@sharadlgsi
@sharadlgsi Жыл бұрын
@@PMPwithRay Thanks a lot for clarification. Really appreciate it.
@PriyaSharma-qw4eb
@PriyaSharma-qw4eb 8 ай бұрын
@@PMPwithRay I have the same doubt, the question states one scenario, and retro happens just after review, on same day or day after. Why should they wait until design phase to tackle this issue
@rugambachristian7587
@rugambachristian7587 Жыл бұрын
3/5 but the last question on Agile was very tricky….thanks Ray.
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@user-to1ws8js5m
@user-to1ws8js5m 5 ай бұрын
5th Question - Project Manager has to tackle this issue, so why not fisrt option is correct? If it's how he could have prevented then option B could be correct. I did 4/5. Thank you so much for your explanation to all questions.
@PMPwithRay
@PMPwithRay 5 ай бұрын
Thank you for participating and commenting!
@aarti444
@aarti444 3 ай бұрын
hi roy. Question 2 , is referring to removal of impediments and impediments are discussed during daily standup . Is there a reason you chose retrospective as an answer ?
@PMPwithRay
@PMPwithRay 3 ай бұрын
Hi Aarti, the reason I chose 'retrospective' is explained in the answer explanation part. Please re-watch that section again and let me know if you still have any doubts.
@kchandrashekar35
@kchandrashekar35 8 ай бұрын
I did all options are right
@PMPwithRay
@PMPwithRay 7 ай бұрын
Good! Thank you for participating and commenting!
@jaybrahmbhatt4744
@jaybrahmbhatt4744 Жыл бұрын
I found 1st and 2nd questions as tricky
@courtneyclarke2999
@courtneyclarke2999 Жыл бұрын
Got 3 out of 5 but haven't studied Agile as yet
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@VBHAT99
@VBHAT99 5 ай бұрын
4/5 Great exercise
@PMPwithRay
@PMPwithRay 5 ай бұрын
Thanks for watching and participating!
@AnoopKumar-ve7bf
@AnoopKumar-ve7bf Жыл бұрын
Three out of 5 for me as well.
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@kratisinghal2677
@kratisinghal2677 Жыл бұрын
Dear sir banning of 2000 re notes is a ambiguity risk or event based risk
@PMPwithRay
@PMPwithRay Жыл бұрын
This would most likely classify as a event based risk.
@venumadhavvaradaraj6141
@venumadhavvaradaraj6141 6 ай бұрын
3/5
@PMPwithRay
@PMPwithRay 6 ай бұрын
Thank you for participating and commenting!
@piyush1651
@piyush1651 Жыл бұрын
4/5 last question was very tough
@PMPwithRay
@PMPwithRay Жыл бұрын
Nice one! Thank you for sharing your score and I believe that you are fairly well prepared for the PMP Exam
@SSMB-mt9zz
@SSMB-mt9zz Жыл бұрын
Hi Ray Any best (close to imitating the exam) websites providing free mock tests / simulators (covering 2023, PMBOK 7)? Thanks.
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for watching and commenting!
@shahedsazal3685
@shahedsazal3685 Жыл бұрын
4/5
@PMPwithRay
@PMPwithRay Жыл бұрын
Nice one! Thank you for sharing your score and I believe that you are fairly well prepared for the PMP Exam
@pareshrone1145
@pareshrone1145 Жыл бұрын
5/5
@PMPwithRay
@PMPwithRay Жыл бұрын
Excellent! I wish you all the best for your PMP Exam. I am sure that you are going to ace it.
@user-rw1hp9eu3b
@user-rw1hp9eu3b Жыл бұрын
4/5, Got the last q wrong and this is the first video I am watching. Adios
@PMPwithRay
@PMPwithRay Жыл бұрын
Nice one! Thank you for sharing your score and I believe that you are fairly well prepared for the PMP Exam
@shivaninimbran5508
@shivaninimbran5508 Жыл бұрын
I scored full
@PMPwithRay
@PMPwithRay Жыл бұрын
Excellent! I wish you all the best for your PMP Exam. I am sure that you are going to ace it.
@rashedulislam1503
@rashedulislam1503 Жыл бұрын
Got 4 out of 5
@PMPwithRay
@PMPwithRay Жыл бұрын
Nice one! Thank you for sharing your score and I believe that you are fairly well prepared for the PMP Exam
@rashedulislam1503
@rashedulislam1503 Жыл бұрын
@@PMPwithRay, thanks ray. Your question is very much tricky and same as like as real exam question.
@jaybrahmbhatt4744
@jaybrahmbhatt4744 Жыл бұрын
I only scored 3/5
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@bimwalaindia
@bimwalaindia 11 ай бұрын
2/5
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@balajimuthu2491
@balajimuthu2491 Жыл бұрын
2.5 for me
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@mohitmalviya4343
@mohitmalviya4343 Жыл бұрын
Only 3 could answer correctly 😢
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@mohitmalviya4343
@mohitmalviya4343 Жыл бұрын
@@PMPwithRay thank you so much for your suggestion.
@nehavlogs441
@nehavlogs441 Жыл бұрын
4/5, last que get wrong
@PMPwithRay
@PMPwithRay Жыл бұрын
Nice one! Thank you for sharing your score and I believe that you are fairly well prepared for the PMP Exam
@nehavlogs441
@nehavlogs441 Жыл бұрын
@@PMPwithRay , not sure but preparation is in progress
@junaidaminkhan8752
@junaidaminkhan8752 Жыл бұрын
3 out of 5😢
@PMPwithRay
@PMPwithRay Жыл бұрын
Thank you for sharing your score. Don’t worry about the score too much. However, focus on your learning gaps and try to improve on the same. The key to a good Exam score is a solid analysis of your mistakes during the practice sessions.
@archanad5611
@archanad5611 4 ай бұрын
3/5
@PMPwithRay
@PMPwithRay 4 ай бұрын
Thank you for participating and commenting
@prayaggokhale7941
@prayaggokhale7941 Жыл бұрын
4/5
@PMPwithRay
@PMPwithRay Жыл бұрын
Nice one! Thank you for sharing your score and I believe that you are fairly well prepared for the PMP Exam
@CethWinch
@CethWinch 11 ай бұрын
4/5
@PMPwithRay
@PMPwithRay 11 ай бұрын
Nice one! Thank you for sharing your score and I believe that you are fairly well prepared for the PMP Exam
Glow Stick Secret Pt.4 😱 #shorts
00:35
Mr DegrEE
Рет қаралды 8 МЛН
艾莎撒娇得到王子的原谅#艾莎
00:24
在逃的公主
Рет қаралды 54 МЛН
LATEST PMP EXAM FORMAT 2024
8:06
CertifyEra Consulting Services
Рет қаралды 5 М.
The Most Important 10 PMP Mindsets to Approach PMP Questions
40:03
The Basics of Good Project Management
1:47:17
CalSouthern BUSINESS
Рет қаралды 1,1 МЛН
50 CAPM Practice Questions for the current Exam
1:10:17
Andrew Ramdayal
Рет қаралды 54 М.