The video addresses some of the Frequently asked questions related to Estimate at Completion (EAC) from Earn value concept.
For instance, you are executing a project which is still undergoing, and you have a defined duration and an identified baseline budget (budget at completion). There comes the point when you analyze your performance, you think can it be possible to complete the project in the previous budget and if not what should be the revised budget (this revised budget is the estimate at completion)? How much money is required to complete this project?
The term used for the required money is ‘estimate to complete.’
EAC= AC (Actual Cost) +ETC (Estimate to complete)
How can you calculate how much more money one needs to complete this project?
What are the three ways to calculate this EAC? And why do we need three ways and not one formula?
What are Atypical variants?
Find answers to these and more interesting questions related to EAC. This is an important topic from PMP® exam point of view.
Do drop your feedback and recommendations for the webinar topics in the comment box.
Subscribe to our KZfaq channel and receive email alerts of latest video upload
The Project Management Professional (PMP), PMBOK, The Agile Certified Practitioner (PMI-ACP), and The Professional in Business Analysis (PMI-PBA) is a registered mark of the Project Management Institute, Inc.
PMBOK is a registered mark of the Project Management Institute, Inc.
Materials in this video are based on the text, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute Inc., 2017.
The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.

Пікірлер: 107
@Blissful8640
@Blissful8640 Жыл бұрын
This is by far the best explanation of EAC calculations on KZfaq
@izenbridge
@izenbridge Жыл бұрын
Thank you.
@cacapoopooface
@cacapoopooface 4 жыл бұрын
This is the clearest anyone has been able to explain EAC to me. Instead of just rote memorization of these formulas, I now have an understanding of what is happening in both the typical and atypical variance cases and when to use either formula. Thank you!
@izenbridge
@izenbridge 4 жыл бұрын
Hi Roger, thanks for your kind words!! Keep an eye on the upcoming videos; we publish them from time to time!!
@Blissful8640
@Blissful8640 Жыл бұрын
I share your sentiments Roger
@basictalent1
@basictalent1 10 жыл бұрын
Thanks alot, this explanation of EAC is so far the best on youtube
@izenbridge
@izenbridge 10 жыл бұрын
Great!!!! basictalent1 you may like to join our Discussion Forum forum.izenbridge.com
@marcoty6312
@marcoty6312 3 жыл бұрын
I guess I'm quite randomly asking but do anybody know of a good website to stream newly released tv shows online?
@jhonnymohammed7351
@jhonnymohammed7351 7 жыл бұрын
I have been searched so many videos for EAC concept....but this one is the best one for me....NICE EXPLANATION sir👌👌👌
@izenbridge
@izenbridge 7 жыл бұрын
Thank you for your kind words :) we are happy to know you found Saket's programs helpful.
@SaurabhGupta-fl1vp
@SaurabhGupta-fl1vp 4 ай бұрын
Best Explanation, now it is crystal clear..... Sir, i followed your videos and successfully passed SAFE6. Now PMP concept is also explained amazingly well. Thanks for the guidance.
@izenbridge
@izenbridge 4 ай бұрын
Thank you for checking our videos , The Earned Value Management Related topics are not that much important in current PMP Exam, You only get two questions and these two also does not require any calculation. I recommend checking our latest Exam trend based PMP Exam Questions explanations series here : kzfaq.info/sun/PLWcvFkRbuunlxAQ92tIt1kXWOcgoyhTRR
@vaishnaviv9850
@vaishnaviv9850 5 жыл бұрын
Hi Saketh, I thought I need to memorize these formulas , now after watching this video I understood the logic and you have made it easy to think and apply this formula in Exam. Tomorrow is my exam :) Thank you , you are the best
@izenbridge
@izenbridge 5 жыл бұрын
Thank you for exploring our videos and for comment here. In general , we make PMP content understandable rather than memorizing it.
@vaishnaviv9850
@vaishnaviv9850 4 жыл бұрын
@@izenbridge I also passed my PMP last month 😀
@angiekourouclis
@angiekourouclis 4 ай бұрын
You possess an extraordinary gift for teaching; your explanations are both straightforward and effortlessly absorbed.
@izenbridge
@izenbridge 4 ай бұрын
Glad it was helpful! The current PMP Exam is not getting into this much details for this topic.
@angiekourouclis
@angiekourouclis 4 ай бұрын
@@izenbridge Thank you, appreciate the input.
@izikrules
@izikrules 8 жыл бұрын
I finally got the concept of EAC!!!! THANK YOU! Keep up the good job!
@izenbridge
@izenbridge 8 жыл бұрын
Thank you :) good to know you our resources helpfull
@sanjujgeo
@sanjujgeo 4 жыл бұрын
Perfectly explained..after so many trials, finally got the concept in brain with this video. Good job Saket!
@izenbridge
@izenbridge 4 жыл бұрын
Keep watching!! To know more about Saket training program, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
@FAMCast
@FAMCast 8 жыл бұрын
From now and on you are my PMP guru sir... Soon will join pmp forum on ur site...
@izenbridge
@izenbridge 8 жыл бұрын
+Faheem Akhter thanks for exploring our program :) stay connected
@akshtsrivastav3021
@akshtsrivastav3021 6 жыл бұрын
You are very good at explaining points. Thanks you for the videos.
@anmarshakir3311
@anmarshakir3311 5 жыл бұрын
You did great job and give the subject most of probability to solve exams.. Thanks a lot
@izenbridge
@izenbridge 5 жыл бұрын
Thank you, we started this channel by solving the Earned Value management problem only. Now we have complete PMBOK 6 program which also has better quality videos, you may like to check our program page for more details: www.izenbridge.com/pmp/online-course/
@rafavaliente741
@rafavaliente741 6 жыл бұрын
Master Zen , please continue showing your mastery
@izenbridge
@izenbridge 6 жыл бұрын
Thanks for exploring our content :) good to know you found it helpful. You can explore our complete content - www.izenbridge.com/pmp/online-course/ You may also drop in your training related queries at sales@izenbridge.com
@artie77cg88
@artie77cg88 9 жыл бұрын
Hi Mr.Pansha. Applying also SPI to calculate EAC... Which will be the final formula within TYPICAL case? Thanks!
@rgsivacts
@rgsivacts 7 жыл бұрын
wonderful explanation... :-) I don't need to memorize these formulas any more..
@hiyer8790
@hiyer8790 7 жыл бұрын
thank you sir! the explanation is fabulous - makes it very simple to follow
@pancycreations
@pancycreations 8 жыл бұрын
Well explained. I have seen the best explanation on this topic in internet
@izenbridge
@izenbridge 8 жыл бұрын
+Rama Krishna thanks for the kind words :) stay connected
@haseebahmed617
@haseebahmed617 5 жыл бұрын
Dear Sir Saket, i have a query, The BAC of a small project is $100,000. So far $40,000 has been spent to deliver work worth $30,000. What will be the cost estimate to finish the project, assuming future work will be done at the budgeted rate? a) $70,000 b) $60,000 c) $110,000 d) $100,000 i have selected option A, because cost estimate to finish (when future work will be done at budgeted rate) formula is ETC=BAC-EV, BAC is 100,000 and EV is 30,000 so ETC becomes 100,000-30,000=70,000$ but correct answer was option C with following Explanation: At the budgeted rate, EAC = AC + (BAC - EV) = 40000 + (100000 - 30000) = $110000. (In this case EAC is the cost to date plus the value of work remaining, assuming budget remains the same). Refer PMBOK Guide 7.4.2.2 Data Analysis (1st bullet, page 265). i have taken cost estimate to finish is estimate to complete ETC please guide.... regards, Haseeb Ahmed.
@izenbridge
@izenbridge 5 жыл бұрын
I think in question it is about ETC , but in answer it is EAC. I think this is an error in question.
@haseebahmed617
@haseebahmed617 5 жыл бұрын
@@izenbridge 👍
@nehatiwary5674
@nehatiwary5674 2 ай бұрын
Thank you so much creating amezing content ❤🙏it's worth watching 🙌😇
@izenbridge
@izenbridge 2 ай бұрын
Thank you so much 😀
@72LINEA
@72LINEA 5 жыл бұрын
Very nicely explained. Drilled the concept . Thanks. It’s certainly a great contribution from you to the project management community.
@Krishnag2409
@Krishnag2409 6 жыл бұрын
The best explanation for EAC...
@projectmanagementwes1716
@projectmanagementwes1716 4 жыл бұрын
Your work is so great I think others could benefit from learning about it.
@izenbridge
@izenbridge 4 жыл бұрын
Thanks for your kind words, keep exploring iZenBridge KZfaq Channel.
@kvc2334
@kvc2334 7 жыл бұрын
Hello! very clear explanation and easy to understand. Thank you
@izenbridge
@izenbridge 7 жыл бұрын
Thank you for exploring our videos :) good to know you found it helpfull
@ZiaSherif
@ZiaSherif 7 жыл бұрын
Very clear explanation. It is indeed really helpful. Thanks
@izenbridge
@izenbridge 7 жыл бұрын
Thanks for exploring our content :) good to know you found it helpful.
@JD-rx2kh
@JD-rx2kh 2 жыл бұрын
This is extremely confusing lol. And it’s part of my job.
@GermanMedinaNeria
@GermanMedinaNeria 5 жыл бұрын
Good , Nice explanation, very clear
@izenbridge
@izenbridge 5 жыл бұрын
Thank you!! Medina for exploring and liking our content. In continuation, you can also watch the following video on "Difference between Total Float & Free Float" kzfaq.info/get/bejne/pJyJfLueuqvTiXU.html
@gulahmad3215
@gulahmad3215 8 жыл бұрын
sir fabulous & conceptual, very nice
@yasirkhan954
@yasirkhan954 2 жыл бұрын
Thanks alot professor. ❤️
@izenbridge
@izenbridge 2 жыл бұрын
Thank you for watching.
@KumaragoudaPatil20
@KumaragoudaPatil20 7 жыл бұрын
Very clearly explained 👌
@izenbridge
@izenbridge 7 жыл бұрын
Thanks for exploring our content :) good to know you found it helpful. You can explore our complete content - www.izenbridge.com/pmp/online-course/ You may also drop in your queries - sales@izenbridge.com
@Zamella1
@Zamella1 5 жыл бұрын
Many thanks!
@izenbridge
@izenbridge 5 жыл бұрын
Thank you !! Zamella, for exploring and liking our content. In Continuation to it, you can explore our video as per PMBOK Guide sixth edition on "Critical Path Method" kzfaq.info/get/bejne/m8CXqZRzvJfQc4k.html
@IoSzMoAnEeL
@IoSzMoAnEeL 7 жыл бұрын
Thank you! very useful! although the third option I didn't get the name correctly in the wb, lol
@prakashlavania3543
@prakashlavania3543 4 жыл бұрын
this explanation is really awesome...
@izenbridge
@izenbridge 4 жыл бұрын
Thanks, Prakash for kind words!! Keep exploring iZenBridge KZfaq Channel.
@darkaouioussama5044
@darkaouioussama5044 9 жыл бұрын
Excellent, Thank you so much
@serioushamster
@serioushamster 5 жыл бұрын
Thank you.
@izenbridge
@izenbridge 5 жыл бұрын
Thanks for exploring and liking our content. You can explore our complete content of PMP (Project Management Professional) Based on PMBOK6 here: www.izenbridge.com/pmp/online-course
@Turkistanian
@Turkistanian 4 жыл бұрын
Hello. Thanks allot professor. Tutorial was awesome and it was really helpful giving detailed information about Estimate At Compilation.
@izenbridge
@izenbridge 4 жыл бұрын
Thanks Khair Salijogy, for your kind words. Happy to know that you found value in the video.
@sudeepm8096
@sudeepm8096 7 жыл бұрын
Flawless Explanation, Cheers!!!
@izenbridge
@izenbridge 7 жыл бұрын
thank you :)
@stax666
@stax666 4 жыл бұрын
Mr. Saket, thank you so much!
@izenbridge
@izenbridge 4 жыл бұрын
Rajon, happy to know that you liked the video!!! Keep watching them. All the best.
@sandy13121987
@sandy13121987 7 жыл бұрын
Nicely explained..
@izenbridge
@izenbridge 7 жыл бұрын
Thanks for exploring our content :) good to know you found it helpful.
@kaviwithshanu-pursuitofper9393
@kaviwithshanu-pursuitofper9393 5 жыл бұрын
superbly explained sir. Thanks. Moreover you like Jackma
@izenbridge
@izenbridge 5 жыл бұрын
Thanks!! Raman for exploring our content and liking it. You can also explore our informative video on EVM inline with PMBOK Guide Sixth edition. kzfaq.info/get/bejne/g7VmeLJ-yZOnm3U.html
@delakofitsigbeh8807
@delakofitsigbeh8807 4 жыл бұрын
Good teacher
@izenbridge
@izenbridge 4 жыл бұрын
Thanks for your kind words!! Happy to know that you liked videos.
@naghmehvahidian
@naghmehvahidian 9 жыл бұрын
excellent, thanks
@gulmohammadkhan9893
@gulmohammadkhan9893 5 жыл бұрын
Very very good
@izenbridge
@izenbridge 5 жыл бұрын
Thank you!! Gul for exploring and liking our content. In continuation to it, you can also explore the PMP video as per PMBOK Guide Sixth edition. Earned Value Management Analysis in simple language kzfaq.info/get/bejne/g7VmeLJ-yZOnm3U.html
@FernandoLoo
@FernandoLoo 8 жыл бұрын
This was really well explained. Thank you!
@izenbridge
@izenbridge 8 жыл бұрын
+Fernando Loo thank you for appreciating :)
@izenbridge
@izenbridge 8 жыл бұрын
+Fernando Loo thank you for appreciating :)
@nocsoc2000
@nocsoc2000 8 жыл бұрын
very useful video
@izenbridge
@izenbridge 8 жыл бұрын
thank you :)
@israallawati6507
@israallawati6507 5 жыл бұрын
Love this. God bless you
@izenbridge
@izenbridge 5 жыл бұрын
Thank you!! Isra for exploring and liking our content. You can also explore our PMP FAQ on Critical Path Method kzfaq.info/get/bejne/h7KhbJCgq9yskoU.html&lc=UgxWZInSK_4fDhD4rbt4AaABAg
@mahmoudaboubakr6526
@mahmoudaboubakr6526 4 жыл бұрын
Fantastic
@izenbridge
@izenbridge 4 жыл бұрын
Thanks, Mahmoud for your kind words, keep exploring iZenBridge KZfaq Channel.
@sourav2328
@sourav2328 6 жыл бұрын
brilliant!
@luckboysunday
@luckboysunday 9 жыл бұрын
I'm trying to find training on project control and scheduling. Can u recommend please? I want to get better as this is currently my full time position. Thax
@izenbridge
@izenbridge 9 жыл бұрын
luckboysunday as of now we only do PMP based program, we do not have specialized scheduling program yet.
@ahmedomar6388
@ahmedomar6388 7 жыл бұрын
You are very beautiful man thank you for these lectures .
@milanshah4
@milanshah4 8 жыл бұрын
bahu saras...!
@piyushsinha1659
@piyushsinha1659 8 жыл бұрын
Awesome
@izenbridge
@izenbridge 8 жыл бұрын
thank you :)
@neel55555
@neel55555 7 жыл бұрын
HOW TO CLAIM PDU FOR THIS LECTURE?
@luckboysunday
@luckboysunday 9 жыл бұрын
When you use the word "EV" is this meaning weekly or total?
@izenbridge
@izenbridge 9 жыл бұрын
luckboysunday It mean at that instance, as part of our cost management plan we need to define at what frequency we are going to do EVM analysis. So EV gets calculated from the start of the project till that point. Please join our forum.izenbridge.com for discussions on PMP related topics
@oscarchoops902
@oscarchoops902 9 жыл бұрын
Very helpful. Thank you. P.S. Fire the camera person.
@izenbridge
@izenbridge 9 жыл бұрын
Oscar Choops if there is any issue with camera or video, please specify, we will surely look after that
@oscarchoops902
@oscarchoops902 9 жыл бұрын
Frame the scene. There's no need to zoom in and out or pan to see a formula or answer. It's very distracting. Thank you again for the informative video. It's appreciated.
@erichchan3
@erichchan3 5 жыл бұрын
My left ear was able to hear it just fine. My right ear fell asleep.
@izenbridge
@izenbridge 5 жыл бұрын
Thankyou!! Eric for exploring our content and sharing your valuable feedback.
@MrKr0307
@MrKr0307 5 жыл бұрын
Cost Variance(CV) = EV-AC not AC-EV
@Awais9428a
@Awais9428a 10 жыл бұрын
Very helpful indeed :)
@izenbridge
@izenbridge 10 жыл бұрын
Awais Mehmood Thanks... You can also join our Forum www.forum.izenbridge.com/
@NiniPa668
@NiniPa668 6 жыл бұрын
Please get a proper camera man
@davidmatlaw7833
@davidmatlaw7833 6 жыл бұрын
forced, sing-song voice
Example of Schedule Network Diagram (CPM) | iZenBridge
9:00
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 17 М.
Project Management Professional (PMP)® | Contract Types | Project Procurement Management
20:41
这三姐弟太会藏了!#小丑#天使#路飞#家庭#搞笑
00:24
家庭搞笑日记
Рет қаралды 56 МЛН
PEDRO PEDRO INSIDEOUT
00:10
MOOMOO STUDIO [무무 스튜디오]
Рет қаралды 14 МЛН
Before VS during the CONCERT 🔥 "Aliby" | Andra Gogan
00:13
Andra Gogan
Рет қаралды 10 МЛН
王子原来是假正经#艾莎
00:39
在逃的公主
Рет қаралды 9 МЛН
Project Management Professional (PMP)®  Earned Value Management : Cost Control | iZenBridge
36:58
Project Management Professional (PMP)® Exam FAQs -  Point of Total Assumption (PTA) ?  iZenBridge
13:12
Project Management Professional (PMP)®  | Estimate Costs  | Project Cost Management
20:41
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 55 М.
Project Management Professional (PMP)®  | Identify Stakeholders | Project Stakeholder Management
15:48
Funding Limit Reconcilation & S-Curve
9:28
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 11 М.
Project Management Professional (PMP)®  | Plan Cost Management| Project Cost Management
10:50
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 23 М.
PMBOK® Guide-Sixth edition : Earned Value Management Analysis
10:08
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 143 М.
这三姐弟太会藏了!#小丑#天使#路飞#家庭#搞笑
00:24
家庭搞笑日记
Рет қаралды 56 МЛН