KiwiRail did an unprecedented work programme from 26 December 2021 to 23 January 2022. It was our most ambitious temporary closure.
To give you a sense of scale, here are some numbers:
- More than 155,000 hours of labour
- 17,000m3 of ballast laid (the small stones that form the track bed
- More than 5km of new rail track
- Installation of 16 complex track structures including turnouts, crossovers and scissors (these allow trains to move from one track to another)