STEP by STEP EXCEL to GANTT CHART | Scheduling Project Management tool | No need for MS Project

  Рет қаралды 32,194

Project Management Mastery

Project Management Mastery

Күн бұрын

Transform Microsoft Excel into a wonderful Gantt Chart (MS Project like) for your Scheduling
✅ 𝙏𝙚𝙢𝙥𝙡𝙖𝙩𝙚
If you did not complete the tutorial and would like to use the template please visit:
www.etsy.com/a...
✅ 𝙊𝙩𝙝𝙚𝙧 𝙂𝙖𝙣𝙩𝙩 𝘾𝙝𝙖𝙧𝙩 𝙬𝙞𝙩𝙝 𝘿𝙚𝙥𝙚𝙣𝙙𝙚𝙣𝙘𝙞𝙚𝙨 𝙖𝙣𝙙 𝘿𝙚𝙡𝙖𝙮𝙨
www.etsy.com/a...
✅ 𝙎𝙝𝙤𝙥
My new Etsy Shop
yourlifeyourpr...
✅ 𝙊𝙣𝙡𝙞𝙣𝙚 𝘾𝙤𝙪𝙧𝙨𝙚𝙨
www.udemy.com/...
𝙈𝙮 𝙤𝙩𝙝𝙚𝙧 𝙔𝙤𝙪𝙏𝙪𝙗𝙚 𝘾𝙝𝙖𝙣𝙣𝙚𝙡𝙨
🎞️ Excel for Home
/ @excelruinedmylife
🎞️ Self Development
/ @yourlifeyourproject
🙏Please consider subscribing for free tutorials on KZfaq and allow me to post more videos like this - That will help me get some traction with YT to provide better content.
Other Excel tutorials:
𝐖𝐚𝐟𝐟𝐥𝐞 𝐂𝐡𝐚𝐫𝐭 𝐢𝐧 𝐄𝐱𝐜𝐞𝐥 • Video
𝐒𝐢𝐦𝐩𝐥𝐞 𝐓𝐚𝐬𝐤 𝐥𝐢𝐬𝐭 𝐢𝐧 𝐄𝐱𝐜𝐞𝐥 • EASY Task tracking Exc...
𝐏𝐨𝐰𝐞𝐫𝐟𝐮𝐥 𝐓𝐚𝐬𝐤 𝐋𝐢𝐬𝐭 𝐢𝐧 𝐄𝐱𝐜𝐞𝐥 • STEP by STEP Task, Pro...
𝐌𝐚𝐤𝐞 𝐲𝐨𝐮𝐫 𝐨𝐰𝐧 𝐄𝐱𝐜𝐞𝐥 𝐑𝐢𝐬𝐤 𝐑𝐞𝐠𝐢𝐬𝐭𝐞𝐫 • STEP by STEP Excel Sma...
𝐌𝐚𝐤𝐞 𝐲𝐨𝐮𝐫 𝐨𝐰𝐧 𝐄𝐱𝐜𝐞𝐥 𝐆𝐚𝐧𝐭𝐭 𝐂𝐡𝐚𝐫𝐭: • STEP by STEP EXCEL to ...
Some videos you might be interested in:
Steering Committee
• Project Management Str...
3 Steps to a Schedule
• Simple Schedule using ...
Courses/Channel topics;
Project Management
Management
MS Project
Time Management
Scheduling
Budget
Issue Management
Issue Log
Project Management fundamentals
Project Management essentials
Project Management 101
Other topics with free tutorials:
Agile
Waterfall
course
project manager
project coordinator
project
course
AMSR tutorial
learning
PMI
PM
PMBOK
Prince2
PMP
Training
Project Management
free training
Steering
Steering committee
Management training
Risk Management
Risk Register
Stress Management
Stakeholder Matrix
Stakeholder Management
Gantt Chart & Scheduling
RAG Status

Пікірлер: 84
@rosieharvey5437
@rosieharvey5437 Жыл бұрын
Thanks for that, great to finally have some dependency on tasks!
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
Glad it was helpful!
@shukhovukakumbi7189
@shukhovukakumbi7189 8 ай бұрын
@@ProjectManagementMastery how do i tick or cross
@ProjectManagementMastery
@ProjectManagementMastery 8 ай бұрын
Not sure what you mean!
@shukhovukakumbi7189
@shukhovukakumbi7189 8 ай бұрын
@@ProjectManagementMastery there is a column called on track, my question is how do I cross or tick an activity to show whether its no track or not
@ProjectManagementMastery
@ProjectManagementMastery 8 ай бұрын
The walkthrough of the Excel will show you that. It is a conditional field with a different font. All the best with it.
@AdjectivesRGreaterThanPronouns
@AdjectivesRGreaterThanPronouns 6 ай бұрын
This is awesome!!! Thank You so much!!! This appears to be working on Google Sheets if anybody is wondering..
@ProjectManagementMastery
@ProjectManagementMastery 6 ай бұрын
@AdjectivesRGreaterThanPronouns Thanks for your comment! And Yes I was wondering - didn't think of trying myself. Great tip!
@amywilliams5176
@amywilliams5176 Жыл бұрын
I have been looking for a Gantt Chart in Excel for quite a while... This one nails it! Subscribed!
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
Welcome aboard!
@kellykelly5564
@kellykelly5564 Жыл бұрын
Finally a video explaining every step. Thanks for that, made my day.
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
You're welcome!
@rebaziemann3526
@rebaziemann3526 Жыл бұрын
Wow, that looks amazing. Didn't know you could do this in Excel.... I had tried to do something myself but didnt think about using the conditional formatting, will definitely try this. Great vid in any case....
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
You can do it!
@rajkumars974
@rajkumars974 10 ай бұрын
Its great to show some small package schedules in the templates for management understanding. I appreciate your great works. Thanks for this wonderful knowledge sharing👍
@ProjectManagementMastery
@ProjectManagementMastery 10 ай бұрын
Thanks for the feedback! All the best.
@jamesstephenson5391
@jamesstephenson5391 Жыл бұрын
Well I think I'll be using this definitely, thanks for sending the Excel - seems to work for my version of Excel....
@anhlehoai1974
@anhlehoai1974 9 ай бұрын
Absolutely amazing, this really helps me solve a current need without whipping out the project management software.
@ProjectManagementMastery
@ProjectManagementMastery 9 ай бұрын
Thanks for the feedback!
@Bobby-rp3gn
@Bobby-rp3gn Жыл бұрын
Love it! Thanks for sharing.
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
Thanks for watching!🙏
@katelynnmertz7346
@katelynnmertz7346 Жыл бұрын
Great video, this gives MS Project a run for its money (And it's so expensive :-()
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
Yes agreed. I do not know why MS Project is so expensive, maybe because they know it is more for companies than individuals...
@JuanCarlos-rj8md
@JuanCarlos-rj8md Жыл бұрын
This looks great, this video is teaching me Excel also at the same time, some great tips.
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
Great to hear!
@wileywiegand6976
@wileywiegand6976 Жыл бұрын
I will send this at work, they will love it :-)
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
Please do!
@biketiwafula7982
@biketiwafula7982 11 ай бұрын
lovely coaching
@batsaikhanbatmunkh6547
@batsaikhanbatmunkh6547 Ай бұрын
thank you for the wonderful tutorial. Finish day calculation formula was not correct in my guess. Because if WORKDAY(J6-1,C6)-1 is sunday then it is become weekend. How about =IF(Weekend_work="No",WORKDAY(J6-1,C6),J6+C6).
@ProjectManagementMastery
@ProjectManagementMastery Ай бұрын
Cheers! Yes that rings a bell, I think there is another comment on this. THhe latest version has =IF(Weekend_work="N",WORKDAY(J6,C6)-1,J6+C6-1) and the note in the instructions. "Please note that when a task completes a Friday night - and there is no weekend work, the system puts the completion date on a Sunday night. This is to allow the Gantt chart to calculate properly the After Date - as in fact it positions itself the day before the next working day."
@emiliacofer549
@emiliacofer549 Жыл бұрын
Looks really good, thanks!!
@elizabethspencer9829
@elizabethspencer9829 Жыл бұрын
Love it...
@Hanan-tf7kh
@Hanan-tf7kh 10 ай бұрын
Thanks for this step by step explanation. I have one question at 19:00 (Days per cell) how did you custom the format?
@ProjectManagementMastery
@ProjectManagementMastery 9 ай бұрын
Hello thanks for the feedback. I use Custom format to do this. Right click on cell / Format Cell / Custom and you create your own format in this case # "day(s)"
@julielinga
@julielinga 7 ай бұрын
This is awesome thanks! - I need to create a GANTT chart for several years divided into months, but when you type in 30 days, it leaves some months (e.g. december) divided into 2 columns).. I only need months, no weekdays or dates - is there any way to get 1 column per month consistently? 🙂
@ProjectManagementMastery
@ProjectManagementMastery 7 ай бұрын
@JuliesModeVlog Thanks for your comment. When you input 30 days it should be the exact month. I have tried and do not have the problem you have. (Sometimes the month is greyed out if I set "work on weekend" to "N" and the first day of the month is Sat or Sun - which I have just fixed for the 30 day scenario). If you want to send me your version to the email that sent you the template I will have a look...
@julielinga
@julielinga 7 ай бұрын
Thank you so much for the response. It would be amazing if you could have a look - I'm still having the issue, but it would probably make more sense to send my version and highlight the problem! What email can I send it to?@@ProjectManagementMastery
@ProjectManagementMastery
@ProjectManagementMastery 7 ай бұрын
@julielinga So you did not get the template? This will give you my email address. You could ask for it again from the description.
@hugoaaa1
@hugoaaa1 7 ай бұрын
Hi, i'm trying to follow this tutorial, but i'm stuck at the first formula! I really like your dashboard, is it possible for you to explain me how did you do it? Thanks in advance!
@ProjectManagementMastery
@ProjectManagementMastery 7 ай бұрын
Thanks for your comment. Can you please let me know which formula you are referring to?
@eli16820
@eli16820 8 ай бұрын
Its amazing. Thanks Could you please share this template?
@ProjectManagementMastery
@ProjectManagementMastery 8 ай бұрын
OF course - Please check the video description...
@constanceegbokhare3957
@constanceegbokhare3957 8 ай бұрын
Great video! I reached out through the link you gave to request the template but didn't receive any.
@ProjectManagementMastery
@ProjectManagementMastery 8 ай бұрын
Hello! It was sent to you 27-Nov, I have just resent it to you manually, please check in a few minutes... All the best!
@martinargimon730
@martinargimon730 Жыл бұрын
sorry. the problem was on my side KZfaq resolution. Forgive me, Thanks again. regards . martin
@ProjectManagementMastery
@ProjectManagementMastery Жыл бұрын
No worries Martin, I have removed your previous post to avoid confusion.
@shawnsellars128
@shawnsellars128 10 ай бұрын
What are you trying to capture with the "Done Until" Field? I'm trying to figure out how to modify the dates if the Remaining work is more than the initial estimate (ie. bad initial estimate). Thanks a lot. This is a great tool.
@ProjectManagementMastery
@ProjectManagementMastery 10 ай бұрын
Thanks for the feeback! The "Done until" field is used to 1) Show the work done on the Gantt (Deep blue) and 2) report if the task is on track or not. If the task is not completed and done only until a date in the past then I know it's late.
@shawnsellars128
@shawnsellars128 10 ай бұрын
@@ProjectManagementMastery Thanks again
@AA-rk4lw
@AA-rk4lw 7 ай бұрын
Hello, Thanks for your share. Please I want to add holiday to the schedule, and have the end date take it into account. Thank you
@ProjectManagementMastery
@ProjectManagementMastery 7 ай бұрын
Hi. Well adding the holidays without using VB Macros would make the formulas just too complex. Check the monthly cost of MS Project and you'll see why.
@AA-rk4lw
@AA-rk4lw 7 ай бұрын
Thank you@@ProjectManagementMastery
@ProjectManagementMastery
@ProjectManagementMastery 7 ай бұрын
@AA-rk4lw Well Strike that I didnt realize but the function I use can accommodate for a list of holidays so will have a look at that for my next version :-)
@ektakumari1847
@ektakumari1847 11 ай бұрын
At 12.06 mins how did you remove all lines from sheet ?
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
I used data / online / group as explained. Is this what you meant?
@anuragsurve5853
@anuragsurve5853 6 ай бұрын
Hello Sir, I have set weekend working as 'No'. So Suppose my start date is 18th Jan 2024, total days worked = 2days, then done until it's showing as 21st Jan as per the formula, but 21st Jan is Sunday. Please help here as Done until date should not be a weekend date as I marked Weekend working as 'No'
@ProjectManagementMastery
@ProjectManagementMastery 6 ай бұрын
@anuragsurve5853 Yes I know... This is the way Excel calculates the end of a working period, if you finish a Friday night it will put the Sunday night as an end date. To start with I thought it was odd but come to think of it is not a bad idea. And it makes all calculation much easier. Having said that I will find a way to change the display end date in my next version.
@PankajSharma-ec6mt
@PankajSharma-ec6mt 11 ай бұрын
Nice template. Do i get the excel file?
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
Thanks for the feedback. Please Check the description for the template!
@wesleypeterson4555
@wesleypeterson4555 9 ай бұрын
So I need help, I did the "same" "after" formula just the way you did. The same works but the After does not... is there a reason why?
@ProjectManagementMastery
@ProjectManagementMastery 9 ай бұрын
Should work... Try and download the template and check it out!
@hanisalehal-ssenai1431
@hanisalehal-ssenai1431 7 ай бұрын
@anuragsurve5853
@anuragsurve5853 7 ай бұрын
Hi, This chart shows done even on weekends, if I have set work on weekends as No
@ProjectManagementMastery
@ProjectManagementMastery 7 ай бұрын
Hello, If you have set work on weekends to No, the weekends should be greyed out - and weekends not counted as working days. Please download the template again and let us know...
@andrewgiffen6898
@andrewgiffen6898 11 ай бұрын
I'm getting an error in the "finish" column. I believe it has to do with the Weekend_work="N"... Any suggestions?
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
Hi Andrew. I just tried to reproduce an error but simply can't do it! Try to evaluate the Formula and see if there is something wrong with your dates...
@KindLittles
@KindLittles 11 ай бұрын
I am having the same issue
@yunnys5796
@yunnys5796 6 ай бұрын
If "days per cell" is not 1, how can I resolve the issue of Today being omitted in Conditional Formatting?
@ProjectManagementMastery
@ProjectManagementMastery 6 ай бұрын
I really dont know what you are referring to!
@anuragsurve5853
@anuragsurve5853 7 ай бұрын
Hi, how can we include public holidays in workday function, Please help.
@ProjectManagementMastery
@ProjectManagementMastery 7 ай бұрын
In my next version!
@user-by2ry4il2t
@user-by2ry4il2t 11 ай бұрын
nice video, may i get the template?
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
Hello - You should have the link in the description - good luck!
@ektakumari1847
@ektakumari1847 11 ай бұрын
At 13.50 how did u got that normal font "u" which is there , couldn't find in excel
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
You should bring back the wingding font directly with the tick. The u is just the wingding tick when you change the font to normal (ie arial or the likes)
@KindLittles
@KindLittles 11 ай бұрын
I'm getting an error in the "finish" column also. I have followed all your steps but it keeps coming up as an error. Do you have an email so I can share screenshots? I've been working on figuring it out for hours now and to no avail.
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
Hi! I'm happy to help. The best way is for you to send me another template request, and instead of your name put "I need help with Gantt". This way I will have your email address and we can start exchanging on your issue
@KindLittles
@KindLittles 11 ай бұрын
@@ProjectManagementMastery how do I send a template request?
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
The first thing is to start using words like "please" and "thank you" I know we are in a digital world but we can still be polite specially when making requests.
@KindLittles
@KindLittles 11 ай бұрын
@@ProjectManagementMastery I wanted to take a moment to apologize for my previous messages and also provide some context for my communication. First and foremost, I want to express my sincere apologies if my previous messages came across as curt or lacking in politeness. Your feedback about maintaining a courteous tone in digital communication is entirely valid, and I genuinely appreciate your perspective. To provide some context, when I sent the initial message, I was admittedly frustrated and at my wit's end. I had spent several hours trying to work through the issue while simultaneously looking after my two young children. It was a challenging situation, and I found myself repeatedly going through the steps to resolve the issue, only to discover that something appeared to be flawed. In my state of frustration, I reached out to ChatGPT for assistance, hoping for a solution but to no avail. What added to my frustration was noticing that another user was facing the same problem, which seemed to indicate a broader issue with the steps in the video. This realization compounded my sense of exasperation. Your feedback serves as a valuable reminder of the importance of maintaining politeness and courtesy in our interactions, regardless of the circumstances. I wholeheartedly agree that showing respect and gratitude through phrases like "please" and "thank you" is essential, and I genuinely appreciate this reminder. I want to assure you that your feedback has not gone unnoticed.
@ProjectManagementMastery
@ProjectManagementMastery 11 ай бұрын
Hi there - thanks for that and I understand your frustration. Of note: These templates are more to provide an Excel demo and providing ideas rather than providing a workable template. Now if you have created the Excel yourself then I would rather not get involved (I am sure you understand why), but if you download the template (check in the description of the video for the link) and try to use it and the problem persists I can have a quick look for you no problem. I would need your Excel copy and some screen shots if the problem needs to be highlighted. To access the template there is a link in the description. Thanks again.
Make This Awesome Gantt Chart in Excel (for Project Management)
17:13
Kenji Explains
Рет қаралды 274 М.
How to Make a Gantt Chart in Excel
12:54
Vertex42
Рет қаралды 3,7 МЛН
Joker can't swim!#joker #shorts
00:46
Untitled Joker
Рет қаралды 41 МЛН
Кадр сыртындағы қызықтар | Келінжан
00:16
How to Make the BEST Gantt Chart in Excel (looks like Microsoft Project!)
15:59
Power Gantt Chart (Project Planner) for Project Management
26:27
PK: An Excel Expert
Рет қаралды 93 М.
How to Create a Gantt Chart in Google Sheets
10:41
Vertex42
Рет қаралды 913 М.