How to Remove Actual from Updated Project in Primavera P6 | Remove Progress | Change Activity Status

  Рет қаралды 5,034

SoftEdemy

SoftEdemy

Күн бұрын

#Softedemy,#PrimaveraP6,#RemoveActual
It takes a lot of time and notification box confirmation while removing the progress of thousands of activities. I have come up with a short solution in this video. In this video, you will learn
How to Remove Actual from Updated Project in Primavera P6 | Remove Progress | Change Activity Status
Time Stamps
0:00 Introduction to Actual Removal Process
0:39 Common Activity Status Change Practices.
01:29 Change Activity Calculation method to remaining Duration reset
02:00 Remove Actual Labor Cost and Units by Global Change
03:34 Remove Actual Non-Labor Cost and Units by Global Change
04:55 Remove Actual Material Cost and Units by Global Change
05:48 Remove Actual Expense Cost and Percentage by Global Change
06:26 Change Activity Status to Not Started by Global Change
08:10 Update Schedule to Project Start date
09:10 Overview of Complete Activity Status Change Process
09:40 Closing out of Video
Related Video Link
Update Progress using Activity Steps | Create Template | Performance Percent | Primavera P6 | Tips |
• Update Progress using ...
How to Create Activity Steps to Update Physical Progress | Primavera P6 |19.12 | Advanced Tutorial
• How to Create Activity...
How to Apply Actual Auto Compute Progress | Primavera P6 |19.12 | Advanced Tutorial
• How to Apply Actual Au...
How to Update Resource Schedule Progress | S Curve | Earned Value Curves | Advanced Tutorial
• How to Update Resource...
How to Update Progress | Primavera P6 | 19.12 | Beginners Tutorial
• How to Update Progress...
Contact Details
Email for Contact: Softedemy@gmail.com
Facebook Group Link: tinyurl.com/yzn34hct
LinkedIn Page: tinyurl.com/ke44khv8

Пікірлер: 9
@mahansor8295
@mahansor8295 Жыл бұрын
Very informative, thanks
@SoftEdemy
@SoftEdemy Жыл бұрын
Welcome
@hendawyragabelashry553
@hendawyragabelashry553 3 жыл бұрын
thanks for valuable information's , hope to prepare one for recovery schedule
@SoftEdemy
@SoftEdemy 3 жыл бұрын
Welcome, Thanks to you too for commenting for improvement. Yes sure i will make video content. In which we will discuss all Planning and Scheduling Professional Practices .My brother you have to switch us .It will take time. Moreover every Schedule have different strategic sequencing .So we will move from general to complex. we will ensure our highest peek level knowledge to viewers in future. So remain tuned with us share it further for better approach .
@mahansor8295
@mahansor8295 Жыл бұрын
Hi, could you please provide a tutorial specifically about the setting and options , and the way to approach, particularly for cost an resources and how the settings affect the project scheduling and other consequences. Thanks again for your professional tutorials.
@SoftEdemy
@SoftEdemy Жыл бұрын
relevant to settings you can watch this playlist . kzfaq.info/sun/PLLVSNbP19zMaZix74ue8MWVU23k5yGVbY Project scheduling setting and options will be explained in upcoming videos . thanks for advance for your question. It will be beneficial for others also.
@mahansor8295
@mahansor8295 Жыл бұрын
I will look through them , thanks again 🙏
@SoftEdemy
@SoftEdemy Жыл бұрын
@@mahansor8295 sure
@SoftEdemy
@SoftEdemy 2 жыл бұрын
For any query contact us on our email : info@softedemy.com
🤔Какой Орган самый длинный ? #shorts
00:42
3M❤️ #thankyou #shorts
00:16
ウエスP -Mr Uekusa- Wes-P
Рет қаралды 15 МЛН
🔴 How to Apply Actual and Update Progress Works in Primavera P6
7:32
import progress updates with actual dates to primavera p6
10:32
Planning Engineer FZE.
Рет қаралды 22 М.
Project Schedule Constraints - Part 1
12:52
Plan Academy Inc.
Рет қаралды 5 М.