Resource Allocation & Leveling - Project Management - Tutorial & Example

  Рет қаралды 99,460

AF Math & Engineering

AF Math & Engineering

5 жыл бұрын

Resource allocation and leveling are important parts of any engineering project. Learn them from this tutorial and example!
-----------------------------------------------------------------------------------------------------------
Now try to solve it on your OWN! Don't just "understand"... PRACTICE!!
-----------------------------------------------------------------------------------------------------------
AF MATH AND ENGINEERING - Students Helping Students!
Join our Community! =)
-------------------------------------
Follow us on Twitter at / afmatheng
Follow us on Facebook at AFMath1/?fre...
#math #civilengineering #engineering #education #edchat #lrnchat #blendchat #mlearning #elearning #ipadchat #pblchat #passiondriven #blendedlearning #ccchat #ccss #commoncore #competencyed #curriculum #deeperlearning #digln #earlyed #edapp #eddata #edleaders #edpolicy #edtech #education #elearning #highschool #leadership #middleschool #literacy #engchat #mathchat #scichat #stem #highered #calculus

Пікірлер: 29
@talk2minie
@talk2minie 3 жыл бұрын
This was very helpful! I was able to complete my course homework thanks to your explanation.Thank you very much!
@Chichi-ez1xo
@Chichi-ez1xo 2 жыл бұрын
My goodness!!! Where have you been the last 2 years of my life?!!!!!! Thank you Thank you very much! this was very helpful, well detailed and specifically explained!
@adityapatel8701
@adityapatel8701 2 жыл бұрын
As activity E depends on completion of activity C. It is not possible to keep both on same day. To lower the labor demand we will have to extend the duration of the project by one day.
@AFMathandEngineering
@AFMathandEngineering 5 жыл бұрын
At the end of the video we place Task 'C' and Task 'E' at the same day. As this is a Start to Finish relationship we can assume that the work will first start with assignment C and only once 'C' is done 'E' will start. We can do that as long as the question/project permits us to perform two tasks at the same day. when you think about it, it makes sense that first we pave and only later we demobilize. However, if we would have a curing time that requires a day or the question would specify that only one task is allowed per day we would have to further allocate the task. If this would be the case we would probably delay the project by one day. Check this link for the rest of our videos on project management! kzfaq.info/sun/PLv11OuQcvb_C5j9lt9ijPIndiNqBEBh-C
@andrewmurschel2608
@andrewmurschel2608 28 күн бұрын
This also makes the assumption that task C can pause once started. Bear in mind that some tasks cannot pause like that without negative facets.
@vp-xk3rt
@vp-xk3rt 4 жыл бұрын
Thank you sir Your explanation is very accurate and to the point Helped me a lot for my exams
@AFMathandEngineering
@AFMathandEngineering 4 жыл бұрын
Glad to hear! Thanks!
@AFMathandEngineering
@AFMathandEngineering 3 жыл бұрын
If you liked this video check out our Project Management Cheat Sheet Tutorial video in the link below. kzfaq.info/get/bejne/gKx_ZLN63rard40.html
@Orthodox19.
@Orthodox19. 2 жыл бұрын
Your explanation is very accurate and to the point i.e it was very easy to understand SO Keep it up !!!@
@anhtruong2636
@anhtruong2636 2 жыл бұрын
Very good and funny videos bring a great sense of entertainment!
@benyang6546
@benyang6546 2 жыл бұрын
so touching for an excellent video
@navnithrajsn1705
@navnithrajsn1705 3 жыл бұрын
Very nicely explained thanks
@quizzlerprofessor
@quizzlerprofessor 3 жыл бұрын
Helpful content thanks
@mongezinkandi6544
@mongezinkandi6544 4 күн бұрын
Can you please clarify this for me, the task C part that you reallocated to day 13, how did you do it, hence the task E depends on tasks C and D? I hope you'll get my question. Thanks in advance
@SadamHussain-yx4sl
@SadamHussain-yx4sl Жыл бұрын
Thank you for solution. Sir, I little bit confusion here because, we have Total Flot of activity C is 4, but we shift labour (8) five time why?
@balamuruganr6840
@balamuruganr6840 3 жыл бұрын
If i want to use all 15 labors every day, what should i do? Thanks in advance.
@btpex536
@btpex536 Жыл бұрын
Sir actually there is a mistake as C latest finish time is 12 but u took it too 13 which is not correct.
@samuelbabarinsa8044
@samuelbabarinsa8044 4 жыл бұрын
but C is a predecessor of E so if the last activity of C comes to the day when E is meant to start, that means E cant start, because C has not finished .....what do you think?
@AFMathandEngineering
@AFMathandEngineering 3 жыл бұрын
See my comment above.
@edlakaumbi8619
@edlakaumbi8619 2 ай бұрын
yes and it is also 4 days long, so will it not delay the project?
@elizemach
@elizemach 3 жыл бұрын
LF of activity C is day 12 - and you alocated it to day 13???
@engsingla85
@engsingla85 Жыл бұрын
Pl resolve this conflict
@ahmeddesoky3599
@ahmeddesoky3599 8 ай бұрын
Thank you for the effort. I've noticed that the date you used in your example are not that precise. At the end you'll end up extending the project by 1 day.
@saharincuker7718
@saharincuker7718 4 жыл бұрын
Excellent Video! Sorry for chiming in, I am interested in your thoughts. Have you considered - Teannah Psychic Sucker (Sure I saw it on Google)? It is a good one off product for finding the best project management and business templates minus the headache. Ive heard some interesting things about it and my coo-worker after many years got amazing results with it.
@AFMathandEngineering
@AFMathandEngineering 4 жыл бұрын
Actually I am not really familiar with that method.
@samratparajuli6032
@samratparajuli6032 2 жыл бұрын
muhaah !!!
@carmenalcala6947
@carmenalcala6947 4 жыл бұрын
Great video content! Excuse me for chiming in, I would love your opinion. Have you thought about - Teannah Psychic Sucker (Have a quick look on google cant remember the place now)? It is a good one off product for finding the best project management and business templates without the normal expense. Ive heard some super things about it and my work buddy at last got amazing results with it.
@user-xq2mv2lb9p
@user-xq2mv2lb9p 2 жыл бұрын
동영상에 있는 상당히 불쾌한 이미지
@somethingdoesntaddup8413
@somethingdoesntaddup8413 3 жыл бұрын
4:13 modern feminist TRIGGERED
PMBOK® Guide: Resource Optimization - Resource Levelling & Resource Smoothing
8:05
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 96 М.
What is Resource Smoothing? (Resource Histogram Example)
7:43
Pieter Rademeyer
Рет қаралды 2,5 М.
Looks realistic #tiktok
00:22
Анастасия Тарасова
Рет қаралды 101 МЛН
ТАМАЕВ УНИЧТОЖИЛ CLS ВЕНГАЛБИ! Конфликт с Ахмедом?!
25:37
Русалка
01:00
История одного вокалиста
Рет қаралды 6 МЛН
That's how money comes into our family
00:14
Mamasoboliha
Рет қаралды 11 МЛН
Difficult network diagram example with lag solved
12:37
Engineer4Free
Рет қаралды 348 М.
Problem on Resource levelling,  resource allocation,  Resource scheduling for project
27:01
Edutech Guru Engineering Learning-By Priyanka ma'am
Рет қаралды 16 М.
Resource leveling and allocation
29:35
Principles of construction management
Рет қаралды 31 М.
Resource Optimization: What's the Difference between Resource Leveling and Resource Smoothing?
7:34
Resource Leveling
6:03
AbleSim
Рет қаралды 27 М.
MS Project Resources - Resource Types and Allocation
12:31
Radu Popa
Рет қаралды 30 М.
Looks realistic #tiktok
00:22
Анастасия Тарасова
Рет қаралды 101 МЛН